1 |
09 Feb 2023
|
Harish Pangti
|
Registration Granted
|
Approved.
|
2 |
30 Jan 2023
|
Anil Kumar Pangty
|
In-Process
|
@Harish Pangti(010096072) ji, Application has been forwarded to you, kindly do the needfull. comments : मुख्य अभियंता (नि) सत्यापन की कार्यवाही पूर्ण हो चूकी है, श्रेणी ए में Bridge कार्य हेतु पंजीकरण की कार्यवाही की सकती है। अवलाकनार्थ/आदेशार्थ प्रस्तुत
|
3 |
28 Jan 2023
|
Kedar Singh
|
In-Process
|
@Anil Kumar Pangty(010096073) ji, Application has been forwarded to you, kindly do the needfull. comments : S.S.O. Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Bridge कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत।
|
4 |
28 Jan 2023
|
Kedar Singh
|
In-Process
|
work Construction and Maintenance(5 Years) 90 Mtr Span Steel Girder Bridge at Km 1 Thirang to Salang L034 Package No UT13133 has been approved by Kedar Singh
|
5 |
28 Jan 2023
|
Kedar Singh
|
In-Process
|
work Construction and Maintenance(5Years) of 24 Span Steel Girder at Km 3.75 DT Road at Kumarkoat, L037 Package No UT13103 has been approved by Kedar Singh
|
6 |
28 Jan 2023
|
Kedar Singh
|
In-Process
|
work Construction and (5Year) of 24 Mtr Span Steel Girder Bridge at Km 2.325 Bayana to Sayawa L039 Package No UT13102 has been approved by Kedar Singh
|
7 |
28 Jan 2023
|
Kedar Singh
|
In-Process
|
work Construction and Maintenance(5 Year) of 36 Mtr Span Steel Girder Bridge at Km 3 (Chainage 2/20 to 2/22) Jamak_Bayana, L038 Package No (UT13104) has been approved by Kedar Singh
|
8 |
28 Jan 2023
|
Kedar Singh
|
In-Process
|
work Construction and Maintenance (5 Year ) of 48 Mtr Span Steel Girder Bridge Pacm 1010) Saura SDari(Malla_Silla) to Pilang L035 Package No. (UT13132) has been approved by Kedar Singh
|
9 |
24 Jan 2023
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Construction and Maintenance(5Years) of 24 Span Steel Girder at Km 3.75 DT Road at Kumarkoat, L037 Package No UT13103
|
10 |
24 Jan 2023
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Construction and Maintenance(5 Years) 90 Mtr Span Steel Girder Bridge at Km 1 Thirang to Salang L034 Package No UT13133
|
11 |
24 Jan 2023
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Construction and Maintenance(5 Year) of 36 Mtr Span Steel Girder Bridge at Km 3 (Chainage 2/20 to 2/22) Jamak_Bayana, L038 Package No (UT13104)
|
12 |
24 Jan 2023
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Construction and (5Year) of 24 Mtr Span Steel Girder Bridge at Km 2.325 Bayana to Sayawa L039 Package No UT13102
|
13 |
24 Jan 2023
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Construction and Maintenance (5 Year ) of 48 Mtr Span Steel Girder Bridge Pacm 1010) Saura SDari(Malla_Silla) to Pilang L035 Package No. (UT13132)
|
14 |
24 Jan 2023
|
Yogamber Singh Rawat
|
Comments
|
Application Forwarded to Parkeen Team.
|
15 |
24 Jan 2023
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
16 |
23 Jan 2023
|
Kedar Singh
|
Reverted
|
Please upload Authorization Letter and ITR. EXp. certificate mismatch.
|
17 |
23 Jan 2023
|
Yogamber Singh Rawat
|
Comments
|
Application Forwarded to Parkeen Team.
|
18 |
23 Jan 2023
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|