1 |
09 Mar 2023
|
Harish Pangti
|
Registration Granted
|
Approved.
|
2 |
30 Jan 2023
|
Anil Kumar Pangty
|
In-Process
|
@Harish Pangti(010096072) ji, Application has been forwarded to you, kindly do the needfull. comments : मुख्य अभियंता (नि) सत्यापन की कार्यवाही पूर्ण हो चूकी है, श्रेणी ए में मार्ग कार्य हेतु पंजीकरण की कार्यवाही की सकती है। अवलाकनार्थ/आदेशार्थ प्रस्तुत
|
3 |
25 Jan 2023
|
Kedar Singh
|
In-Process
|
@Anil Kumar Pangty(010096073) ji, Application has been forwarded to you, kindly do the needfull. comments : S.S.O. Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत।
|
4 |
25 Jan 2023
|
Kedar Singh
|
In-Process
|
work Construction of km. 18 of MDR 33 motor road to Sawai motor road under PMGSY stage_II. has been approved by Kedar Singh
|
5 |
25 Jan 2023
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Construction of km. 18 of MDR 33 motor road to Sawai motor road under PMGSY stage_II.
|
6 |
25 Jan 2023
|
Yogamber Singh Rawat
|
In-Process
|
Application Forwarded to Parkeen Team.
|
7 |
25 Jan 2023
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
8 |
25 Jan 2023
|
Kedar Singh
|
Reverted
|
अनुभव प्रमाण पत्र 1 के सत्यापित प्रति में अधिश्ससी अभियंता के ह0 नहीं है। ।
|
9 |
21 Jan 2023
|
Anil Kumar Pangty
|
In-Process
|
@Mahendra Kumar(420010235) ji, Application has been forwarded to you, kindly do the needfull. comments : अनुभव प्रमाण पत्र 1 के सत्यापित प्रति में अधिश्ससी अभियंता के ह0 नहीं है। । Letter - Authorization में Partnership Deed लगी है। आवश्यक कार्यवाही की प्रस्तुत करें।
|
10 |
17 Jan 2023
|
Mahendra Kumar
|
In-Process
|
@Anil Kumar Pangty(010096073) ji, Application has been forwarded to you, kindly do the needfull. comments : S.S.O. Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत।
|
11 |
17 Jan 2023
|
Mahendra Kumar
|
In-Process
|
work Restoration work of Langha_Toli to Binhaar motor road under PMGSY phase_X has been approved by Mahendra Kumar
|
12 |
13 Jan 2023
|
Mahendra Kumar
|
In-Process
|
Mail Has been send for Verification of work Restoration work of Langha_Toli to Binhaar motor road under PMGSY phase_X
|
13 |
13 Jan 2023
|
Mahendra Kumar
|
In-Process
|
work Work of M.D.R. 33 km. 18 to Sawai motor road Stage_II. has been approved by Mahendra Kumar
|
14 |
13 Jan 2023
|
Mahendra Kumar
|
In-Process
|
work Restoration work of M.D.R. 33 km. 18 to Sawai motor road under PMGSY phase_VIII has been approved by Mahendra Kumar
|
15 |
13 Jan 2023
|
Mahendra Kumar
|
In-Process
|
work Construction of Kharsi to Khatwa Motor road under PMGSY. has been approved by Mahendra Kumar
|
16 |
13 Jan 2023
|
Mahendra Kumar
|
In-Process
|
work Construction of km. 18 of MDR 33 motor road to Sawai motor road under PMGSY stage_II. has been approved by Mahendra Kumar
|
17 |
11 Jan 2023
|
Mahendra Kumar
|
In-Process
|
Mail Has been send for Verification of work Restoration work of M.D.R. 33 km. 18 to Sawai motor road under PMGSY phase_VIII
|
18 |
11 Jan 2023
|
Mahendra Kumar
|
In-Process
|
Mail Has been send for Verification of work Restoration work of Langha_Toli to Binhaar motor road under PMGSY phase_X
|
19 |
11 Jan 2023
|
Mahendra Kumar
|
In-Process
|
Mail Has been send for Verification of work Construction of Kharsi to Khatwa Motor road under PMGSY.
|
20 |
11 Jan 2023
|
Mahendra Kumar
|
In-Process
|
Mail Has been send for Verification of work Work of M.D.R. 33 km. 18 to Sawai motor road Stage_II.
|
21 |
11 Jan 2023
|
Mahendra Kumar
|
In-Process
|
Mail Has been send for Verification of work Construction of km. 18 of MDR 33 motor road to Sawai motor road under PMGSY stage_II.
|
22 |
09 Jan 2023
|
Anil Kumar Pangty
|
Comments
|
@Mahendra Kumar(420010235) ji, Application has been forwarded to you, kindly do the needfull. comments : समस्त प्रमाण पत्रों को सत्यापन कर प्रस्तुत करें।
|
23 |
09 Jan 2023
|
Mahendra Kumar
|
Comments
|
@Anil Kumar Pangty(010096073) ji, Application has been forwarded to you, kindly do the needfull. comments : S.S.O. Sir अनुभव प्रमाण पत्र/हेसियत/चरित्र प्रमाण पत्र के सत्यापन की कार्यवाही हेतु आदेशित करना चाहे।
|
24 |
04 Jan 2023
|
Mahendra Kumar
|
Comments
|
@Anil Kumar Pangty(010096073) ji, Application has been forwarded to you, kindly do the needfull. comments : S.S.O. Sir अनुभव प्रमाण पत्र/हेसियत/चरित्र प्रमाण पत्र के सत्यापन की कार्यवाही हेतु आदेशित करना चाहे।
|
25 |
04 Jan 2023
|
Yogamber Singh Rawat
|
Comments
|
Application Forwarded to Parkeen Team.
|
26 |
04 Jan 2023
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
27 |
02 Jan 2023
|
Kedar Singh
|
Reverted
|
GST No. Mismatch. Identity of Rahul Rawat should be uploaded.
|
28 |
19 Dec 2022
|
Yogamber Singh Rawat
|
Comments
|
Application Forwarded to Parkeen Team.
|
29 |
19 Dec 2022
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|