1 |
23 May 2023
|
Girish Chandra Arya
|
Registration Granted
|
As per verification, approval and recommendation by concern officers and employees.
|
2 |
19 May 2023
|
Prem Singh Nabiyal
|
In-Process
|
@Girish Chandra Arya(010099552) ji, Application has been forwarded to you, kindly do the needfull. comments : As per the recommendation of EE the registration may be accorded in the category A road works.
|
3 |
27 Apr 2023
|
Balram Misra
|
In-Process
|
@Prem Singh Nabiyal(570068221) ji, Application has been forwarded to you, kindly do the needfull. comments : Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत। Pay slip of technical staff has been uploaded in Memorandum of Understanding
|
4 |
26 Apr 2023
|
Kedar Singh
|
In-Process
|
@Balram Misra(420010048) ji, Application has been forwarded to you, kindly do the needfull. comments : EE Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत। Pay slip of technical staff has been uploaded in Memorandum of Understanding
|
5 |
19 Apr 2023
|
Yogamber Singh Rawat
|
In-Process
|
Application Forwarded to Parkeen Team.
|
6 |
19 Apr 2023
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
7 |
29 Mar 2023
|
Kedar Singh
|
Reverted
|
submit pay slip of technical staff
|
8 |
24 Mar 2023
|
Balram Misra
|
In-Process
|
@Kedar Singh(010090330) ji, Application has been forwarded to you, kindly do the needfull. comments : Application has been forwarded to you, kindly do the needfull. comments : please do needful check and put up
|
9 |
23 Mar 2023
|
Prem Singh Nabiyal
|
In-Process
|
@Balram Misra(420010048) ji, Application has been forwarded to you, kindly do the needfull. comments : please do needful check and put up
|
10 |
07 Feb 2023
|
Anil Kumar Pangty
|
In-Process
|
@Kedar Singh(010090330) ji, Application has been forwarded to you, kindly do the needfull. comments : वैधिक सलाहाकार (LA) की राय हेतु पत्रावली प्रेषित है। वैधिक सलाहाकार की राय के उपरान्त प्रकरण प्रस्तुत करें।
|
11 |
25 Jan 2023
|
Kedar Singh
|
In-Process
|
@Anil Kumar Pangty(010096073) ji, Application has been forwarded to you, kindly do the needfull. comments : S.S.O. Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत।
|
12 |
25 Jan 2023
|
Kedar Singh
|
In-Process
|
work Construction of Retaining wall NH_72A(307) has been approved by Kedar Singh
|
13 |
25 Jan 2023
|
Kedar Singh
|
In-Process
|
work Construction work of Retaining wall under NH_72A has been approved by Kedar Singh
|
14 |
25 Jan 2023
|
Kedar Singh
|
In-Process
|
work Under the State plan , construction of road from village to river in village Bairagiwala under Vikasnagar Vidhan Sabha.plan has been approved by Kedar Singh
|
15 |
25 Jan 2023
|
Kedar Singh
|
In-Process
|
work Reconstruction and reinforcement work of various motor roads by pc and cc from main road to Barat Ghar in Luthapur motor road under Pauri Garhwal Distt. has been approved by Kedar Singh
|
16 |
25 Jan 2023
|
Kedar Singh
|
In-Process
|
work ROAD CONSTRUCTION FOR GURUDWARA IN Km. 3 OF DEHRADUN RAIPUR ROAD UNDER STATE PLAN has been approved by Kedar Singh
|
17 |
13 Jan 2023
|
Mahendra Kumar
|
In-Process
|
Mail Has been send for Verification of work Under the State plan , construction of road from village to river in village Bairagiwala under Vikasnagar Vidhan Sabha.plan
|
18 |
11 Jan 2023
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Under the State plan , construction of road from village to river in village Bairagiwala under Vikasnagar Vidhan Sabha.plan
|
19 |
11 Jan 2023
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Forwarded to Parkeen Team.
|
20 |
11 Jan 2023
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
21 |
09 Jan 2023
|
Mahendra Kumar
|
Reverted
|
Letter number and date is not mentioned in 3rd no. experience Certificate.
|
22 |
19 Dec 2022
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Under the State plan , construction of road from village to river in village Bairagiwala under Vikasnagar Vidhan Sabha.plan
|
23 |
19 Dec 2022
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work ROAD CONSTRUCTION FOR GURUDWARA IN Km. 3 OF DEHRADUN RAIPUR ROAD UNDER STATE PLAN
|
24 |
09 Dec 2022
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Under the State plan , construction of road from village to river in village Bairagiwala under Vikasnagar Vidhan Sabha.plan
|
25 |
09 Dec 2022
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Reconstruction and reinforcement work of various motor roads by pc and cc from main road to Barat Ghar in Luthapur motor road under Pauri Garhwal Distt.
|
26 |
09 Dec 2022
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work ROAD CONSTRUCTION FOR GURUDWARA IN Km. 3 OF DEHRADUN RAIPUR ROAD UNDER STATE PLAN
|
27 |
05 Dec 2022
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Construction of Retaining wall NH_72A(307)
|
28 |
05 Dec 2022
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Construction work of Retaining wall under NH_72A
|
29 |
30 Nov 2022
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Construction work of Retaining wall under NH_72A
|
30 |
30 Nov 2022
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Construction of Retaining wall NH_72A(307)
|
31 |
30 Nov 2022
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Under the State plan , construction of road from village to river in village Bairagiwala under Vikasnagar Vidhan Sabha.plan
|
32 |
30 Nov 2022
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Reconstruction and reinforcement work of various motor roads by pc and cc from main road to Barat Ghar in Luthapur motor road under Pauri Garhwal Distt.
|
33 |
30 Nov 2022
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work ROAD CONSTRUCTION FOR GURUDWARA IN Km. 3 OF DEHRADUN RAIPUR ROAD UNDER STATE PLAN
|
34 |
22 Nov 2022
|
Anil Kumar Pangty
|
Comments
|
@Kedar Singh(010090330) ji, Application has been forwarded to you, kindly do the needfull. comments : प्रमाण पत्रों को सत्यापन करें
|
35 |
21 Nov 2022
|
Kedar Singh
|
Comments
|
@Anil Kumar Pangty(010096073) ji, Application has been forwarded to you, kindly do the needfull. comments : S.S.O. Sir अनुभव प्रमाण पत्र/हेसियत/चरित्र प्रमाण पत्र के सत्यापन की कार्यवाही हेतु आदेशित करना चाहे।
|
36 |
19 Nov 2022
|
Yogamber Singh Rawat
|
Comments
|
Application Forwarded to Parkeen Team.
|
37 |
19 Nov 2022
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
38 |
18 Nov 2022
|
Kedar Singh
|
Reverted
|
Experience Certificate mismatch. Partnership deed not clear. ITR not clear. 1 exp. is belong to bridge.
|
39 |
18 Nov 2022
|
Yogamber Singh Rawat
|
Comments
|
Application Forwarded to Parkeen Team.
|
40 |
18 Nov 2022
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
41 |
11 Oct 2022
|
Kedar Singh
|
Reverted
|
Shri Sandeep Semwal Character certificate not clear. Tech. staff Sanju malik also working with other contractor. Sandeep ITR not clear. 2nd no. exp. certificate is belong to bridge and 5th no. exp. certificate is belong to singage.
|
42 |
10 Oct 2022
|
Yogamber Singh Rawat
|
Comments
|
Application Forwarded to Parkeen Team.
|
43 |
10 Oct 2022
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|