Dashboard Contractor Registration

Contractor Application No. 54542 for Category Road Class A Applied Office : E-n-C Office Applied On Date : 13 Apr 2023

23 May 2023

Status : Registration Granted

By: Girish Chandra Arya

As per verification, approval and recommendation by concern officers and employees.

19 May 2023

Status : In-Process

By: Prem Singh Nabiyal

@Girish Chandra Arya(010099552) ji, Application has been forwarded to you, kindly do the needfull. comments : As per the recommendation of EE the registration may be accorded in the category A road works.

27 Apr 2023

Status : In-Process

By: Balram Misra

@Prem Singh Nabiyal(570068221) ji, Application has been forwarded to you, kindly do the needfull. comments : Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत। Pay slip of technical staff has been uploaded in Memorandum of Understanding

26 Apr 2023

Status : In-Process

By: Kedar Singh

@Balram Misra(420010048) ji, Application has been forwarded to you, kindly do the needfull. comments : EE Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत। Pay slip of technical staff has been uploaded in Memorandum of Understanding

19 Apr 2023

Status : In-Process

By: Yogamber Singh Rawat

Application Forwarded to Parkeen Team.

19 Apr 2023

Status : Acknowledged

By: Yogamber Singh Rawat

Application Acknoledged.

29 Mar 2023

Status : Reverted

By: Kedar Singh

submit pay slip of technical staff

24 Mar 2023

Status : In-Process

By: Balram Misra

@Kedar Singh(010090330) ji, Application has been forwarded to you, kindly do the needfull. comments : Application has been forwarded to you, kindly do the needfull. comments : please do needful check and put up

23 Mar 2023

Status : In-Process

By: Prem Singh Nabiyal

@Balram Misra(420010048) ji, Application has been forwarded to you, kindly do the needfull. comments : please do needful check and put up

07 Feb 2023

Status : In-Process

By: Anil Kumar Pangty

@Kedar Singh(010090330) ji, Application has been forwarded to you, kindly do the needfull. comments : वैधिक सलाहाकार (LA) की राय हेतु पत्रावली प्रेषित है। वैधिक सलाहाकार की राय के उपरान्त प्रकरण प्रस्तुत करें।

25 Jan 2023

Status : In-Process

By: Kedar Singh

@Anil Kumar Pangty(010096073) ji, Application has been forwarded to you, kindly do the needfull. comments : S.S.O. Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत।

25 Jan 2023

Status : In-Process

By: Kedar Singh

work Construction of Retaining wall NH_72A(307) has been approved by Kedar Singh

25 Jan 2023

Status : In-Process

By: Kedar Singh

work Construction work of Retaining wall under NH_72A has been approved by Kedar Singh

25 Jan 2023

Status : In-Process

By: Kedar Singh

work Under the State plan , construction of road from village to river in village Bairagiwala under Vikasnagar Vidhan Sabha.plan has been approved by Kedar Singh

25 Jan 2023

Status : In-Process

By: Kedar Singh

work Reconstruction and reinforcement work of various motor roads by pc and cc from main road to Barat Ghar in Luthapur motor road under Pauri Garhwal Distt. has been approved by Kedar Singh

25 Jan 2023

Status : In-Process

By: Kedar Singh

work ROAD CONSTRUCTION FOR GURUDWARA IN Km. 3 OF DEHRADUN RAIPUR ROAD UNDER STATE PLAN has been approved by Kedar Singh

13 Jan 2023

Status : In-Process

By: Mahendra Kumar

Mail Has been send for Verification of work Under the State plan , construction of road from village to river in village Bairagiwala under Vikasnagar Vidhan Sabha.plan

11 Jan 2023

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work Under the State plan , construction of road from village to river in village Bairagiwala under Vikasnagar Vidhan Sabha.plan

11 Jan 2023

Status : Acknowledged

By: Yogamber Singh Rawat

Application Forwarded to Parkeen Team.

11 Jan 2023

Status : Acknowledged

By: Yogamber Singh Rawat

Application Acknoledged.

09 Jan 2023

Status : Reverted

By: Mahendra Kumar

Letter number and date is not mentioned in 3rd no. experience Certificate.

19 Dec 2022

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work Under the State plan , construction of road from village to river in village Bairagiwala under Vikasnagar Vidhan Sabha.plan

19 Dec 2022

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work ROAD CONSTRUCTION FOR GURUDWARA IN Km. 3 OF DEHRADUN RAIPUR ROAD UNDER STATE PLAN

09 Dec 2022

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work Under the State plan , construction of road from village to river in village Bairagiwala under Vikasnagar Vidhan Sabha.plan

09 Dec 2022

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work Reconstruction and reinforcement work of various motor roads by pc and cc from main road to Barat Ghar in Luthapur motor road under Pauri Garhwal Distt.

09 Dec 2022

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work ROAD CONSTRUCTION FOR GURUDWARA IN Km. 3 OF DEHRADUN RAIPUR ROAD UNDER STATE PLAN

05 Dec 2022

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work Construction of Retaining wall NH_72A(307)

05 Dec 2022

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work Construction work of Retaining wall under NH_72A

30 Nov 2022

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work Construction work of Retaining wall under NH_72A

30 Nov 2022

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work Construction of Retaining wall NH_72A(307)

30 Nov 2022

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work Under the State plan , construction of road from village to river in village Bairagiwala under Vikasnagar Vidhan Sabha.plan

30 Nov 2022

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work Reconstruction and reinforcement work of various motor roads by pc and cc from main road to Barat Ghar in Luthapur motor road under Pauri Garhwal Distt.

30 Nov 2022

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work ROAD CONSTRUCTION FOR GURUDWARA IN Km. 3 OF DEHRADUN RAIPUR ROAD UNDER STATE PLAN

22 Nov 2022

Status : Comments

By: Anil Kumar Pangty

@Kedar Singh(010090330) ji, Application has been forwarded to you, kindly do the needfull. comments : प्रमाण पत्रों को सत्यापन करें

21 Nov 2022

Status : Comments

By: Kedar Singh

@Anil Kumar Pangty(010096073) ji, Application has been forwarded to you, kindly do the needfull. comments : S.S.O. Sir अनुभव प्रमाण पत्र/हेसियत/चरित्र प्रमाण पत्र के सत्यापन की कार्यवाही हेतु आदेशित करना चाहे।

19 Nov 2022

Status : Comments

By: Yogamber Singh Rawat

Application Forwarded to Parkeen Team.

19 Nov 2022

Status : Acknowledged

By: Yogamber Singh Rawat

Application Acknoledged.

18 Nov 2022

Status : Reverted

By: Kedar Singh

Experience Certificate mismatch. Partnership deed not clear. ITR not clear. 1 exp. is belong to bridge.

18 Nov 2022

Status : Comments

By: Yogamber Singh Rawat

Application Forwarded to Parkeen Team.

18 Nov 2022

Status : Acknowledged

By: Yogamber Singh Rawat

Application Acknoledged.

11 Oct 2022

Status : Reverted

By: Kedar Singh

Shri Sandeep Semwal Character certificate not clear. Tech. staff Sanju malik also working with other contractor. Sandeep ITR not clear. 2nd no. exp. certificate is belong to bridge and 5th no. exp. certificate is belong to singage.

10 Oct 2022

Status : Comments

By: Yogamber Singh Rawat

Application Forwarded to Parkeen Team.

10 Oct 2022

Status : Acknowledged

By: Yogamber Singh Rawat

Application Acknoledged.


Sl No On Date Officer Status Remarks
1 23 May 2023 Girish Chandra Arya Registration Granted As per verification, approval and recommendation by concern officers and employees.
2 19 May 2023 Prem Singh Nabiyal In-Process @Girish Chandra Arya(010099552) ji, Application has been forwarded to you, kindly do the needfull. comments : As per the recommendation of EE the registration may be accorded in the category A road works.
3 27 Apr 2023 Balram Misra In-Process @Prem Singh Nabiyal(570068221) ji, Application has been forwarded to you, kindly do the needfull. comments : Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत। Pay slip of technical staff has been uploaded in Memorandum of Understanding
4 26 Apr 2023 Kedar Singh In-Process @Balram Misra(420010048) ji, Application has been forwarded to you, kindly do the needfull. comments : EE Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत। Pay slip of technical staff has been uploaded in Memorandum of Understanding
5 19 Apr 2023 Yogamber Singh Rawat In-Process Application Forwarded to Parkeen Team.
6 19 Apr 2023 Yogamber Singh Rawat Acknowledged Application Acknoledged.
7 29 Mar 2023 Kedar Singh Reverted submit pay slip of technical staff
8 24 Mar 2023 Balram Misra In-Process @Kedar Singh(010090330) ji, Application has been forwarded to you, kindly do the needfull. comments : Application has been forwarded to you, kindly do the needfull. comments : please do needful check and put up
9 23 Mar 2023 Prem Singh Nabiyal In-Process @Balram Misra(420010048) ji, Application has been forwarded to you, kindly do the needfull. comments : please do needful check and put up
10 07 Feb 2023 Anil Kumar Pangty In-Process @Kedar Singh(010090330) ji, Application has been forwarded to you, kindly do the needfull. comments : वैधिक सलाहाकार (LA) की राय हेतु पत्रावली प्रेषित है। वैधिक सलाहाकार की राय के उपरान्त प्रकरण प्रस्तुत करें।
11 25 Jan 2023 Kedar Singh In-Process @Anil Kumar Pangty(010096073) ji, Application has been forwarded to you, kindly do the needfull. comments : S.S.O. Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत।
12 25 Jan 2023 Kedar Singh In-Process work Construction of Retaining wall NH_72A(307) has been approved by Kedar Singh
13 25 Jan 2023 Kedar Singh In-Process work Construction work of Retaining wall under NH_72A has been approved by Kedar Singh
14 25 Jan 2023 Kedar Singh In-Process work Under the State plan , construction of road from village to river in village Bairagiwala under Vikasnagar Vidhan Sabha.plan has been approved by Kedar Singh
15 25 Jan 2023 Kedar Singh In-Process work Reconstruction and reinforcement work of various motor roads by pc and cc from main road to Barat Ghar in Luthapur motor road under Pauri Garhwal Distt. has been approved by Kedar Singh
16 25 Jan 2023 Kedar Singh In-Process work ROAD CONSTRUCTION FOR GURUDWARA IN Km. 3 OF DEHRADUN RAIPUR ROAD UNDER STATE PLAN has been approved by Kedar Singh
17 13 Jan 2023 Mahendra Kumar In-Process Mail Has been send for Verification of work Under the State plan , construction of road from village to river in village Bairagiwala under Vikasnagar Vidhan Sabha.plan
18 11 Jan 2023 Kedar Singh In-Process Mail Has been send for Verification of work Under the State plan , construction of road from village to river in village Bairagiwala under Vikasnagar Vidhan Sabha.plan
19 11 Jan 2023 Yogamber Singh Rawat Acknowledged Application Forwarded to Parkeen Team.
20 11 Jan 2023 Yogamber Singh Rawat Acknowledged Application Acknoledged.
21 09 Jan 2023 Mahendra Kumar Reverted Letter number and date is not mentioned in 3rd no. experience Certificate.
22 19 Dec 2022 Kedar Singh In-Process Mail Has been send for Verification of work Under the State plan , construction of road from village to river in village Bairagiwala under Vikasnagar Vidhan Sabha.plan
23 19 Dec 2022 Kedar Singh In-Process Mail Has been send for Verification of work ROAD CONSTRUCTION FOR GURUDWARA IN Km. 3 OF DEHRADUN RAIPUR ROAD UNDER STATE PLAN
24 09 Dec 2022 Kedar Singh In-Process Mail Has been send for Verification of work Under the State plan , construction of road from village to river in village Bairagiwala under Vikasnagar Vidhan Sabha.plan
25 09 Dec 2022 Kedar Singh In-Process Mail Has been send for Verification of work Reconstruction and reinforcement work of various motor roads by pc and cc from main road to Barat Ghar in Luthapur motor road under Pauri Garhwal Distt.
26 09 Dec 2022 Kedar Singh In-Process Mail Has been send for Verification of work ROAD CONSTRUCTION FOR GURUDWARA IN Km. 3 OF DEHRADUN RAIPUR ROAD UNDER STATE PLAN
27 05 Dec 2022 Kedar Singh In-Process Mail Has been send for Verification of work Construction of Retaining wall NH_72A(307)
28 05 Dec 2022 Kedar Singh In-Process Mail Has been send for Verification of work Construction work of Retaining wall under NH_72A
29 30 Nov 2022 Kedar Singh In-Process Mail Has been send for Verification of work Construction work of Retaining wall under NH_72A
30 30 Nov 2022 Kedar Singh In-Process Mail Has been send for Verification of work Construction of Retaining wall NH_72A(307)
31 30 Nov 2022 Kedar Singh In-Process Mail Has been send for Verification of work Under the State plan , construction of road from village to river in village Bairagiwala under Vikasnagar Vidhan Sabha.plan
32 30 Nov 2022 Kedar Singh In-Process Mail Has been send for Verification of work Reconstruction and reinforcement work of various motor roads by pc and cc from main road to Barat Ghar in Luthapur motor road under Pauri Garhwal Distt.
33 30 Nov 2022 Kedar Singh In-Process Mail Has been send for Verification of work ROAD CONSTRUCTION FOR GURUDWARA IN Km. 3 OF DEHRADUN RAIPUR ROAD UNDER STATE PLAN
34 22 Nov 2022 Anil Kumar Pangty Comments @Kedar Singh(010090330) ji, Application has been forwarded to you, kindly do the needfull. comments : प्रमाण पत्रों को सत्यापन करें
35 21 Nov 2022 Kedar Singh Comments @Anil Kumar Pangty(010096073) ji, Application has been forwarded to you, kindly do the needfull. comments : S.S.O. Sir अनुभव प्रमाण पत्र/हेसियत/चरित्र प्रमाण पत्र के सत्यापन की कार्यवाही हेतु आदेशित करना चाहे।
36 19 Nov 2022 Yogamber Singh Rawat Comments Application Forwarded to Parkeen Team.
37 19 Nov 2022 Yogamber Singh Rawat Acknowledged Application Acknoledged.
38 18 Nov 2022 Kedar Singh Reverted Experience Certificate mismatch. Partnership deed not clear. ITR not clear. 1 exp. is belong to bridge.
39 18 Nov 2022 Yogamber Singh Rawat Comments Application Forwarded to Parkeen Team.
40 18 Nov 2022 Yogamber Singh Rawat Acknowledged Application Acknoledged.
41 11 Oct 2022 Kedar Singh Reverted Shri Sandeep Semwal Character certificate not clear. Tech. staff Sanju malik also working with other contractor. Sandeep ITR not clear. 2nd no. exp. certificate is belong to bridge and 5th no. exp. certificate is belong to singage.
42 10 Oct 2022 Yogamber Singh Rawat Comments Application Forwarded to Parkeen Team.
43 10 Oct 2022 Yogamber Singh Rawat Acknowledged Application Acknoledged.