Contractor Application No. 49942 for Category Road Class A Applied Office : E-n-C Office Applied On Date : 04 Aug 2022

07 Sep 2022

Status : Reverted

By: Arvind Kumar Singh

1. Work at S.No. 2 - Experience certificate clearly shows work executed under the head of bridge / protection work. So, the bridge work needs to be separated from road part, if any. So, amended certificate should be uploaded and then examined and verified. 2. Work at S.No. 4 - Repair of pipeline cannot be a road work. So, this also be deducted from road part. Upload amended certificate

20 Aug 2022

Status : In-Process

By: Mukesh Singh Parmar

@Arvind Kumar Singh(010089541) ji, Application has been forwarded to you, kindly do the needfull. comments : 1. Work at S.No. 2 - Experience certificate clearly shows work executed under the head of bridge / protection work. So, the bridge work needs to be separated from road part, if any. So, amended certificate should be uploaded and then examined and verified. 2. Work at S.No. 4 - Repair of pipeline cannot be a road work. So, this also be deducted from road part. Upload amended certificate

19 Aug 2022

Status : In-Process

By: Ashok Kumar

@Mukesh Singh Parmar(010099551) ji, Application has been forwarded to you, kindly do the needfull. comments : 1. Work at S.No. 2 - Experience certificate clearly shows work executed under the head of bridge / protection work. So, the bridge work needs to be separated from road part, if any. So, amended certificate should be uploaded and then examined and verified. 2. Work at S.No. 4 - Repair of pipeline cannot be a road work. So, this also be deducted from road part. Upload amended certificate.

17 Aug 2022

Status : In-Process

By: Mukesh Singh Parmar

@Ashok Kumar(42270213M00002) ji, Application has been forwarded to you, kindly do the needfull. comments : Sir, in sl no. 2 according to work detail sent by concern division in varification, item of works are RRdry. further sl no 4 items are RCC Wire crate and RR 1:6 done also while repair of pipelines works done under civil works which was damaged by road can not be treated as building works . As per nature of these items registration may done. hence recommended for enlistment pl.

11 Aug 2022

Status : In-Process

By: Ashok Kumar

@Mukesh Singh Parmar(010099551) ji, Application has been forwarded to you, kindly do the needfull. comments : 1. Experience certificate of work at S.No. 2 consists of work of bridge also. The value of work of bridge should not be included in the work done as registration is for roads. So, upload amended certificate. 2. Experience certificate of work at S.No. 4 consists of work of repair of pipe line which is not acceptable.

08 Aug 2022

Status : In-Process

By: Mukesh Singh Parmar

@Ashok Kumar(42270213M00002) ji, Application has been forwarded to you, kindly do the needfull. comments : recommended for registration pl.

08 Aug 2022

Status : In-Process

By: Mukesh Singh Parmar

@Ashok Kumar(42270213M00002) ji, Application has been forwarded to you, kindly do the needfull. comments : recommended for registration pl.

08 Aug 2022

Status : In-Process

By: Arvind Kumar Singh

@Mukesh Singh Parmar(010099551) ji, Application has been forwarded to you, kindly do the needfull. comments : महोदय, कृपया ठेकेदार के चरित्र प्रमाण पत्र एवं हैसियत प्रमाण पत्र का सत्यापन ऑन लाइन कर लिया गया है। ठेकेदार द्वारा प्रस्तुत अनुभव प्रमाण पत्र के सत्यापन हेतु सम्बन्धित कार्यालयों द्वारा सत्यापन की पुष्टि की गई है। जिसे अपलोड किया गया है। प्राप्त अभिलेखों के आधार पर ठेकेदार का मार्ग कार्य हेतु पंजीकरण किये जाने की सामान्यतः औपचारिकतायें पूर्ण हैं। अतः श्री लोकेन्द्र सिंह राणा, टिहरी गढ़वाल का मार्ग कार्यो’ हेतु श्रेणी ’ए’ में विभाग में पंजीकरण करना चाहे। कृपया अवलोकनार्थ/आदेशार्थ प्रस्तुत।

08 Aug 2022

Status : In-Process

By: Arvind Kumar Singh

work Chardham karya yojna ke antargat kshatigrast motor marg ke prambhik bhag mei crash barrier dwara surakshatmak karya has been approved by Arvind Kumar Singh

08 Aug 2022

Status : In-Process

By: Arvind Kumar Singh

work Koti raulyaluki se borgaon tak motor marg se kshatigrast pipe line va paidal kshatigrast margo ka punha nirman has been approved by Arvind Kumar Singh

08 Aug 2022

Status : In-Process

By: Arvind Kumar Singh

work Koti raulyaluki se borgaon motor marg ke KM 2 va 3 mei kshatigrast divaron ka punha nirman has been approved by Arvind Kumar Singh

08 Aug 2022

Status : In-Process

By: Arvind Kumar Singh

work Koti raulyaluki se borgaon motor marg ke Km 2 mei kshatigrast pul va marg ka surakshatmak karya has been approved by Arvind Kumar Singh

08 Aug 2022

Status : In-Process

By: Arvind Kumar Singh

work Nagni mandai jaul via jakhot sudara devri nakot nagdev pathld motor marg mei PC dwara navinikaran has been approved by Arvind Kumar Singh

05 Aug 2022

Status : In-Process

By: Arvind Kumar Singh

Mail Has been send for Verification of work Chardham karya yojna ke antargat kshatigrast motor marg ke prambhik bhag mei crash barrier dwara surakshatmak karya

05 Aug 2022

Status : In-Process

By: Arvind Kumar Singh

Mail Has been send for Verification of work Koti raulyaluki se borgaon tak motor marg se kshatigrast pipe line va paidal kshatigrast margo ka punha nirman

05 Aug 2022

Status : In-Process

By: Arvind Kumar Singh

Mail Has been send for Verification of work Koti raulyaluki se borgaon motor marg ke KM 2 va 3 mei kshatigrast divaron ka punha nirman

05 Aug 2022

Status : In-Process

By: Arvind Kumar Singh

Mail Has been send for Verification of work Koti raulyaluki se borgaon motor marg ke Km 2 mei kshatigrast pul va marg ka surakshatmak karya

05 Aug 2022

Status : In-Process

By: Arvind Kumar Singh

Mail Has been send for Verification of work Nagni mandai jaul via jakhot sudara devri nakot nagdev pathld motor marg mei PC dwara navinikaran

05 Aug 2022

Status : Comments

By: Yogamber Singh Rawat

Application Forwarded to Vidhayi Team.

05 Aug 2022

Status : Acknowledged

By: Yogamber Singh Rawat

Application Acknoledged.


Sl No On Date Officer Status Remarks
1 07 Sep 2022 Arvind Kumar Singh Reverted 1. Work at S.No. 2 - Experience certificate clearly shows work executed under the head of bridge / protection work. So, the bridge work needs to be separated from road part, if any. So, amended certificate should be uploaded and then examined and verified. 2. Work at S.No. 4 - Repair of pipeline cannot be a road work. So, this also be deducted from road part. Upload amended certificate
2 20 Aug 2022 Mukesh Singh Parmar In-Process @Arvind Kumar Singh(010089541) ji, Application has been forwarded to you, kindly do the needfull. comments : 1. Work at S.No. 2 - Experience certificate clearly shows work executed under the head of bridge / protection work. So, the bridge work needs to be separated from road part, if any. So, amended certificate should be uploaded and then examined and verified. 2. Work at S.No. 4 - Repair of pipeline cannot be a road work. So, this also be deducted from road part. Upload amended certificate
3 19 Aug 2022 Ashok Kumar In-Process @Mukesh Singh Parmar(010099551) ji, Application has been forwarded to you, kindly do the needfull. comments : 1. Work at S.No. 2 - Experience certificate clearly shows work executed under the head of bridge / protection work. So, the bridge work needs to be separated from road part, if any. So, amended certificate should be uploaded and then examined and verified. 2. Work at S.No. 4 - Repair of pipeline cannot be a road work. So, this also be deducted from road part. Upload amended certificate.
4 17 Aug 2022 Mukesh Singh Parmar In-Process @Ashok Kumar(42270213M00002) ji, Application has been forwarded to you, kindly do the needfull. comments : Sir, in sl no. 2 according to work detail sent by concern division in varification, item of works are RRdry. further sl no 4 items are RCC Wire crate and RR 1:6 done also while repair of pipelines works done under civil works which was damaged by road can not be treated as building works . As per nature of these items registration may done. hence recommended for enlistment pl.
5 11 Aug 2022 Ashok Kumar In-Process @Mukesh Singh Parmar(010099551) ji, Application has been forwarded to you, kindly do the needfull. comments : 1. Experience certificate of work at S.No. 2 consists of work of bridge also. The value of work of bridge should not be included in the work done as registration is for roads. So, upload amended certificate. 2. Experience certificate of work at S.No. 4 consists of work of repair of pipe line which is not acceptable.
6 08 Aug 2022 Mukesh Singh Parmar In-Process @Ashok Kumar(42270213M00002) ji, Application has been forwarded to you, kindly do the needfull. comments : recommended for registration pl.
7 08 Aug 2022 Mukesh Singh Parmar In-Process @Ashok Kumar(42270213M00002) ji, Application has been forwarded to you, kindly do the needfull. comments : recommended for registration pl.
8 08 Aug 2022 Arvind Kumar Singh In-Process @Mukesh Singh Parmar(010099551) ji, Application has been forwarded to you, kindly do the needfull. comments : महोदय, कृपया ठेकेदार के चरित्र प्रमाण पत्र एवं हैसियत प्रमाण पत्र का सत्यापन ऑन लाइन कर लिया गया है। ठेकेदार द्वारा प्रस्तुत अनुभव प्रमाण पत्र के सत्यापन हेतु सम्बन्धित कार्यालयों द्वारा सत्यापन की पुष्टि की गई है। जिसे अपलोड किया गया है। प्राप्त अभिलेखों के आधार पर ठेकेदार का मार्ग कार्य हेतु पंजीकरण किये जाने की सामान्यतः औपचारिकतायें पूर्ण हैं। अतः श्री लोकेन्द्र सिंह राणा, टिहरी गढ़वाल का मार्ग कार्यो’ हेतु श्रेणी ’ए’ में विभाग में पंजीकरण करना चाहे। कृपया अवलोकनार्थ/आदेशार्थ प्रस्तुत।
9 08 Aug 2022 Arvind Kumar Singh In-Process work Chardham karya yojna ke antargat kshatigrast motor marg ke prambhik bhag mei crash barrier dwara surakshatmak karya has been approved by Arvind Kumar Singh
10 08 Aug 2022 Arvind Kumar Singh In-Process work Koti raulyaluki se borgaon tak motor marg se kshatigrast pipe line va paidal kshatigrast margo ka punha nirman has been approved by Arvind Kumar Singh
11 08 Aug 2022 Arvind Kumar Singh In-Process work Koti raulyaluki se borgaon motor marg ke KM 2 va 3 mei kshatigrast divaron ka punha nirman has been approved by Arvind Kumar Singh
12 08 Aug 2022 Arvind Kumar Singh In-Process work Koti raulyaluki se borgaon motor marg ke Km 2 mei kshatigrast pul va marg ka surakshatmak karya has been approved by Arvind Kumar Singh
13 08 Aug 2022 Arvind Kumar Singh In-Process work Nagni mandai jaul via jakhot sudara devri nakot nagdev pathld motor marg mei PC dwara navinikaran has been approved by Arvind Kumar Singh
14 05 Aug 2022 Arvind Kumar Singh In-Process Mail Has been send for Verification of work Chardham karya yojna ke antargat kshatigrast motor marg ke prambhik bhag mei crash barrier dwara surakshatmak karya
15 05 Aug 2022 Arvind Kumar Singh In-Process Mail Has been send for Verification of work Koti raulyaluki se borgaon tak motor marg se kshatigrast pipe line va paidal kshatigrast margo ka punha nirman
16 05 Aug 2022 Arvind Kumar Singh In-Process Mail Has been send for Verification of work Koti raulyaluki se borgaon motor marg ke KM 2 va 3 mei kshatigrast divaron ka punha nirman
17 05 Aug 2022 Arvind Kumar Singh In-Process Mail Has been send for Verification of work Koti raulyaluki se borgaon motor marg ke Km 2 mei kshatigrast pul va marg ka surakshatmak karya
18 05 Aug 2022 Arvind Kumar Singh In-Process Mail Has been send for Verification of work Nagni mandai jaul via jakhot sudara devri nakot nagdev pathld motor marg mei PC dwara navinikaran
19 05 Aug 2022 Yogamber Singh Rawat Comments Application Forwarded to Vidhayi Team.
20 05 Aug 2022 Yogamber Singh Rawat Acknowledged Application Acknoledged.