1 |
08 Sep 2022
|
Ashok Kumar
|
Registration Granted
|
Approved provisionally
|
2 |
07 Sep 2022
|
Mukesh Singh Parmar
|
In-Process
|
@Ashok Kumar(42270213M00002) ji, Application has been forwarded to you, kindly do the needfull. comments : Advice received from Legal advisor, according to seek advice experience of individual partner should count fully for the firm.
recommended for enlistment accordingly.
|
3 |
20 Aug 2022
|
Mukesh Singh Parmar
|
In-Process
|
@Arvind Kumar Singh(010089541) ji, Application has been forwarded to you, kindly do the needfull. comments : Seek legal advice.
|
4 |
19 Aug 2022
|
Ashok Kumar
|
In-Process
|
@Mukesh Singh Parmar(010099551) ji, Application has been forwarded to you, kindly do the needfull. comments : Seek legal advice.
|
5 |
16 Aug 2022
|
Mukesh Singh Parmar
|
In-Process
|
@Ashok Kumar(42270213M00002) ji, Application has been forwarded to you, kindly do the needfull. comments : Dear Sir,
The experience of 100 % of single partner will be considered in case of experience of firm.
|
6 |
09 Aug 2022
|
Ashok Kumar
|
In-Process
|
@Mukesh Singh Parmar(010099551) ji, Application has been forwarded to you, kindly do the needfull. comments : Experience certificates for works at S.No. 1, 2 & 3 have been executed by one of the partners of the applicant firm. Examine whether these experiences qualify for the firm keeping in view share of that partner in the applicant firm.
|
7 |
06 Aug 2022
|
Mukesh Singh Parmar
|
In-Process
|
@Ashok Kumar(42270213M00002) ji, Application has been forwarded to you, kindly do the needfull. comments : recommended for registration pl.
|
8 |
05 Aug 2022
|
Mukesh Singh Parmar
|
In-Process
|
@Ashok Kumar(42270213M00002) ji, Application has been forwarded to you, kindly do the needfull. comments : recommended for registration pl.
|
9 |
04 Aug 2022
|
Arvind Kumar Singh
|
In-Process
|
@Mukesh Singh Parmar(010099551) ji, Application has been forwarded to you, kindly do the needfull. comments : महोदय,
कृपया फर्म के तीनों भागीदारों के चरित्र प्रमाण पत्र का सत्यापन ऑन लाइन कर लिया गया है तथा फर्म द्वारा प्रस्तुत बैंक सोलवेन्सी के सत्यापन हेतु सम्बन्धित बैंक को पत्र लिखा गया था। उक्त के अनुपालन में बैंक द्वारा अपने स्तर से जारी करने की पुष्टि करते हुए ऑन लाइन प्रेषित किया गया है। फर्म द्वारा प्रस्तुत अनुभव प्रमाण पत्र के सत्यापन हेतु सम्बन्धित कार्यालयों को पत्र लिखा गया था। उक्त के अनुपालन में सम्बन्धित कार्यालयों द्वारा सत्यापन की पुष्टि कर ऑन लाइन प्रेषित की गई है। कुछ अनुभव प्रमाण पत्र का सत्यापन कार्यालय स्तर से पूर्व में किया जा चुका है। जिसे अपलोड किया गया है। प्राप्त अभिलेखों के आधार पर फर्म का मार्ग कार्य हेतु पंजीकरण किये जाने की सामान्यतः औपचारिकतायें पूर्ण हैं।
अतः मैसर्स चौहान कन्सट्रक्शन डामटा, उत्तरकाशी का मार्ग कार्यो’ हेतु श्रेणी ’ए’ में विभाग में पंजीकरण करना चाहे।
कृपया अवलोकनार्थ/आदेशार्थ प्रस्तुत।
|
10 |
04 Aug 2022
|
Arvind Kumar Singh
|
In-Process
|
work Damta Kandari sarigad motor marg ke KM 1,2,3,4,5,8,12 mei PC dwara navinikaran has been approved by Arvind Kumar Singh
|
11 |
29 Jul 2022
|
Yogamber Singh Rawat
|
Submitted
|
Application Forwarded to Vidhayi Team.
|
12 |
29 Jul 2022
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
13 |
28 Jul 2022
|
Arvind Kumar Singh
|
Reverted
|
UPLOAD POWER OF ATTORNEY
|
14 |
24 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
Mail Has been send for Verification of work Damta Kandari sarigad motor marg ke KM 1,2,3,4,5,8,12 mei PC dwara navinikaran
|
15 |
21 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
Mail Has been send for Verification of work Damta Kandari sarigad motor marg ke KM 1,2,3,4,5,8,12 mei PC dwara navinikaran
|
16 |
18 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
Mail Has been send for Verification of work Damta Kandari sarigad motor marg ke KM 1,2,3,4,5,8,12 mei PC dwara navinikaran
|
17 |
14 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
work Mising link motor marg par pahaad kataan evam scupper ka nirma has been approved by Arvind Kumar Singh
|
18 |
14 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
work Damta Kandari Sarigad mukhya jila ke KM 36 Va 37 mei PC dwara navinikaran has been approved by Arvind Kumar Singh
|
19 |
14 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
work Sarigad Gatu Mulgaon motor marg ka sudharikaran has been approved by Arvind Kumar Singh
|
20 |
14 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
work Sarigad Gatu Mulgan Naugaon motor marg ke jandnu tak motor marg ka nav nirman has been approved by Arvind Kumar Singh
|
21 |
12 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
Mail Has been send for Verification of work Damta Kandari sarigad motor marg ke KM 1,2,3,4,5,8,12 mei PC dwara navinikaran
|
22 |
12 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
Mail Has been send for Verification of work Mising link motor marg par pahaad kataan evam scupper ka nirma
|
23 |
12 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
Mail Has been send for Verification of work Damta Kandari Sarigad mukhya jila ke KM 36 Va 37 mei PC dwara navinikaran
|
24 |
12 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
Mail Has been send for Verification of work Sarigad Gatu Mulgaon motor marg ka sudharikaran
|
25 |
12 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
Mail Has been send for Verification of work Sarigad Gatu Mulgan Naugaon motor marg ke jandnu tak motor marg ka nav nirman
|
26 |
11 Jul 2022
|
Yogamber Singh Rawat
|
Comments
|
Application Forwarded to Vidhayi Team.
|
27 |
11 Jul 2022
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|