1 |
16 Aug 2022
|
Mukesh Singh Parmar
|
Reverted
|
works shown as in experience certificate sl. no 4,5 are not Government entity nor approval from any Govt authority is uploaded . hence reverted for correction.
|
2 |
25 Jul 2022
|
Mukesh Singh Parmar
|
In-Process
|
1. Experience cerificate of work at S.No. 3 has not been uploaded. Uploaded document is just a copy of contract bond. This is not acceptable. 2. Experience certificates of works at S.No. 4 & 5 have not been signed by E.E. or equivalent officer. These certificates are not acceptable. 3. Verify all genuine certificates afresh. SSO should examine before forwarding for enlistment.
|
3 |
24 Jul 2022
|
Ashok Kumar
|
In-Process
|
4. Proper solvency certificate has also not been uploaded.
|
4 |
24 Jul 2022
|
Ashok Kumar
|
In-Process
|
1. Experience cerificate of work at S.No. 3 has not been uploaded. Uploaded document is just a copy of contract bond. This is not acceptable.
2. Experience certificates of works at S.No. 4 & 5 have not been signed by E.E. or equivalent officer. These certificates are not acceptable.
3. Verify all genuine certificates afresh.
SSO should examine before forwarding for enlistment.
|
5 |
14 Jul 2022
|
Mukesh Singh Parmar
|
In-Process
|
Recommended for enlistment pl.
|
6 |
14 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
महोदय,
कृपया ठेकेदार के चरित्र प्रमाण पत्र एवं हैसियत प्रमाण पत्र का सत्यापन ऑन लाइन कर लिया गया है। ठेकेदार द्वारा प्रस्तुत अनुभव प्रमाण पत्र के सत्यापन पूर्व में सम्बन्धित कार्यालयों द्वारा सत्यापन की पुष्टि की गई है। जिसे अपलोड किया गया है। प्राप्त अभिलेखों के आधार पर ठेकेदार का मार्ग कार्य हेतु पंजीकरण किये जाने की सामान्यतः औपचारिकतायें पूर्ण हैं।
अतः श्री पुष्पपाल सिंह खाती, टिहरी गढ़वाल का मार्ग कार्यो’ हेतु श्रेणी ’ए’ में विभाग में पंजीकरण करने पर विचार करना चाहे।
कृपया अवलोकनार्थ/आदेशार्थ प्रस्तुत।
|
7 |
11 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
work Construction of embankment in Doiwala Bypass On NH 72 has been approved by Arvind Kumar Singh
|
8 |
11 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
work Repair And maintainance from haridwar to dehradun section of NH58and72 has been approved by Arvind Kumar Singh
|
9 |
11 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
work Chamroli Sarona motor marg ke akm 3 va 4 mei pahaad kataan has been approved by Arvind Kumar Singh
|
10 |
11 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
work Jajal Hadisera motor marg se gangsar gaon hetu motor marg ka vistar has been approved by Arvind Kumar Singh
|
11 |
11 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
work Chamroli Sarona motor marg KM 3 tatha 4 mei pahaad kataan has been approved by Arvind Kumar Singh
|
12 |
11 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
Mail Has been send for Verification of work Construction of embankment in Doiwala Bypass On NH 72
|
13 |
11 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
Mail Has been send for Verification of work Repair And maintainance from haridwar to dehradun section of NH58and72
|
14 |
11 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
Mail Has been send for Verification of work Chamroli Sarona motor marg ke akm 3 va 4 mei pahaad kataan
|
15 |
11 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
Mail Has been send for Verification of work Jajal Hadisera motor marg se gangsar gaon hetu motor marg ka vistar
|
16 |
11 Jul 2022
|
Arvind Kumar Singh
|
In-Process
|
Mail Has been send for Verification of work Chamroli Sarona motor marg KM 3 tatha 4 mei pahaad kataan
|
17 |
02 Jul 2022
|
Yogamber Singh Rawat
|
Comments
|
Application Forwarded to Vidhayi Team.
|
18 |
02 Jul 2022
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|