1 |
21 Dec 2023
|
Narendra Pant
|
In-Process
|
@Om Prakash(010099553) ji, Application has been forwarded to you, kindly do the needfull. comments : महोदय कृपया एफ0डी0आर0 का सत्यापन प्राप्त हो चुका है अतः पंजीकरण 30.06.2026 तक किया जा सकता है। कृपया आदेशार्थ प्रस्तुत।
|
2 |
30 Nov 2023
|
Om Prakash
|
Registration Granted
|
Approved as per comments of officers and the Section.
|
3 |
16 Oct 2023
|
Manoj Kumar Bisht
|
In-Process
|
@Om Prakash(010099553) ji, Application has been forwarded to you, kindly do the needfull. comments : Sir Documents has been verified, registration may be granted
|
4 |
27 Sep 2023
|
Navneet Pandey
|
In-Process
|
@Manoj Kumar Bisht(010096004) ji, Application has been forwarded to you, kindly do the needfull. comments : uploaded documents verification received , so registration may be process
|
5 |
26 Sep 2023
|
Basant Lal
|
In-Process
|
@Navneet Pandey(020088889426) ji, Application has been forwarded to you, kindly do the needfull. comments : महोदय कृपया ठेकेदार द्वारा अपलाड किये गये अभिलेखों में अनुभव प्रमाण पत्र एवं बैंक सैल्वेसी प्रमाण पत्र का सत्यापन प्राप्त हो चुका है। अतः पंजीकरण हेतु विचार करना चाहें। कृपया अवलोकनार्थ/आदेशार्थ प्रस्तुत।
|
6 |
25 Sep 2023
|
Narendra Pant
|
In-Process
|
@Basant Lal(010022168) ji, Application has been forwarded to you, kindly do the needfull. comments : रिष्ठ प्रशासनिक अधिकारी महोदय कृपया ठेकेदार द्वारा अपलाड किये गये अभिलेखों में अनुभव प्रमाण पत्र एवं बैंक सैल्वेसी प्रमाण पत्र का सत्यापन प्राप्त हो चुका है। अतः पंजीकरण हेतु विचार करना चाहें।
कृपया अवलोकनार्थ/आदेशार्थ प्रस्तुत।
|
7 |
22 Sep 2023
|
Narendra Pant
|
In-Process
|
work Paryatak Vasa Grah Gairsain mein Staff Quater (Type Pratham 2 No. avim type Second 1 No. )ka nirman karya has been approved by Narendra Pant
|
8 |
22 Sep 2023
|
Narendra Pant
|
In-Process
|
work Paryatak Avas Grah Gairsain Ka nirman has been approved by Narendra Pant
|
9 |
22 Sep 2023
|
Narendra Pant
|
In-Process
|
work Conatruction of Stock Man Center Silpata Gairsain has been approved by Narendra Pant
|
10 |
22 Sep 2023
|
Narendra Pant
|
In-Process
|
work Construction of Add Primary Health Center Malsi and Type_1,2nos and Type 2,2nos has been approved by Narendra Pant
|
11 |
22 Sep 2023
|
Narendra Pant
|
In-Process
|
work Vikaskhand Karyalay Bhawan Gairsain Ka Bhawan Nirman Karya has been approved by Narendra Pant
|
12 |
20 Sep 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Paryatak Vasa Grah Gairsain mein Staff Quater (Type Pratham 2 No. avim type Second 1 No. )ka nirman karya
|
13 |
20 Sep 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Paryatak Avas Grah Gairsain Ka nirman
|
14 |
20 Sep 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Conatruction of Stock Man Center Silpata Gairsain
|
15 |
20 Sep 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction of Add Primary Health Center Malsi and Type_1,2nos and Type 2,2nos
|
16 |
20 Sep 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Vikaskhand Karyalay Bhawan Gairsain Ka Bhawan Nirman Karya
|
17 |
11 Sep 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Paryatak Vasa Grah Gairsain mein Staff Quater (Type Pratham 2 No. avim type Second 1 No. )ka nirman karya
|
18 |
11 Sep 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Paryatak Avas Grah Gairsain Ka nirman
|
19 |
11 Sep 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Conatruction of Stock Man Center Silpata Gairsain
|
20 |
11 Sep 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction of Add Primary Health Center Malsi and Type_1,2nos and Type 2,2nos
|
21 |
11 Sep 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Vikaskhand Karyalay Bhawan Gairsain Ka Bhawan Nirman Karya
|
22 |
04 Sep 2023
|
Yogamber Singh Rawat
|
Comments
|
Application Forwarded to Niyojan 3 Team.
|
23 |
04 Sep 2023
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
24 |
02 Sep 2023
|
Narendra Pant
|
Reverted
|
कृपया आप द्वारा अपलोड किये गये अनुभव प्रमाण पत्र में मेल आईडी सही अंकित नही की गयी है। अतः सही मेल आईडी अकित करने का कष्ट करें।
|
25 |
02 Sep 2023
|
Yogamber Singh Rawat
|
In-Process
|
Application Forwarded to Niyojan 3 Team.
|
26 |
02 Sep 2023
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
27 |
30 Aug 2023
|
Narendra Pant
|
Reverted
|
कृपया आप द्वारा अपलोड किये गये अनुभव प्रमाण पत्र में मेल आईडी सही अंकित नही की गयी है। अतः सही मेल आईडी अकित करने का कष्ट करें।
|
28 |
26 Aug 2023
|
Navneet Pandey
|
In-Process
|
@Basant Lal(010022168) ji, Application has been forwarded to you, kindly do the needfull. comments : Application has been forwarded to you, kindly do the needfull. comments : The case is pending.
|
29 |
26 Aug 2023
|
Manoj Kumar Bisht
|
In-Process
|
@Navneet Pandey(020088889426) ji, Application has been forwarded to you, kindly do the needfull. comments : The case is pending.
|
30 |
04 Aug 2023
|
Manoj Kumar Bisht
|
In-Process
|
@Basant Lal(010022168) ji, Application has been forwarded to you, kindly do the needfull. comments : if data is sufficient process application immediately
|
31 |
07 Jun 2023
|
Yogamber Singh Rawat
|
In-Process
|
Application Forwarded to Niyojan 3 Team.
|
32 |
07 Jun 2023
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
33 |
25 May 2023
|
Narendra Pant
|
Reverted
|
कृपया एस0ओ0पी0 के अनुसार तकनीकी स्टाफ में नियुक्त कर्मिकों की वेतन स्पिल अपलोड नही की गयी है। अतः वेतन स्लिप अपलोड करने का कष्ट करें।
|
34 |
06 Mar 2023
|
Narendra Pant
|
In-Process
|
work Paryatak Avas Grah Gairsain ka Nirman has been approved by Narendra Pant
|
35 |
06 Mar 2023
|
Narendra Pant
|
In-Process
|
work Conatruction of Stock Man Center Silpata Gairsain has been approved by Narendra Pant
|
36 |
06 Mar 2023
|
Narendra Pant
|
In-Process
|
work Vikaskhand Karyalay Bhawan Gairsain Ka Bhawan Nirman Karya has been approved by Narendra Pant
|
37 |
06 Mar 2023
|
Narendra Pant
|
In-Process
|
work Construction of Add Primary Health Center Malsi and Type_1,2nos and Type 2,2nos has been approved by Narendra Pant
|
38 |
06 Mar 2023
|
Narendra Pant
|
In-Process
|
work Construction of Staff Quaters type_1 2 nos and Type 11 1Nos and Approach Road at Gairsain has been approved by Narendra Pant
|
39 |
23 Feb 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction of Staff Quaters type_1 2 nos and Type 11 1Nos and Approach Road at Gairsain
|
40 |
23 Feb 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Paryatak Avas Grah Gairsain ka Nirman
|
41 |
23 Feb 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Conatruction of Stock Man Center Silpata Gairsain
|
42 |
23 Feb 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction of Add Primary Health Center Malsi and Type_1,2nos and Type 2,2nos
|
43 |
23 Feb 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Vikaskhand Karyalay Bhawan Gairsain Ka Bhawan Nirman Karya
|
44 |
23 Feb 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Vikaskhand Karyalay Bhawan Gairsain Ka Bhawan Nirman Karya
|
45 |
23 Feb 2023
|
Yogamber Singh Rawat
|
Submitted
|
Application Forwarded to Niyojan 3 Team.
|
46 |
23 Feb 2023
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
47 |
23 Feb 2023
|
Basant Lal
|
Reverted
|
अपलोड किये गये अभिलेखों में तकनीकी स्टाफ के रूप में नियुक्त कर्मिका दो फर्म में कार्यरत है।
|
48 |
21 Feb 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Conatruction of Stock Man Center Silpata Gairsain
|
49 |
21 Feb 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Paryatak Avas Grah Gairsain ka Nirman
|
50 |
21 Feb 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction of Staff Quaters type_1 2 nos and Type 11 1Nos and Approach Road at Gairsain
|
51 |
21 Feb 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction of Add Primary Health Center Malsi and Type_1,2nos and Type 2,2nos
|
52 |
21 Feb 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Vikaskhand Karyalay Bhawan Gairsain Ka Bhawan Nirman Karya
|
53 |
21 Feb 2023
|
Yogamber Singh Rawat
|
Comments
|
Application Forwarded to Niyojan 3 Team.
|
54 |
21 Feb 2023
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
55 |
11 Nov 2022
|
Basant Lal
|
Reverted
|
अपलोड किये गये अभिलेखों में तकनीकी स्टाफ के रूप Provisional Certifcate अपलोड किया गया है।
|
56 |
19 Oct 2022
|
Prem Lata Bisht
|
Comments
|
Application Forwarded to Niyojan 3 Team.
|
57 |
19 Oct 2022
|
Prem Lata Bisht
|
Acknowledged
|
Application Acknoledged.
|
58 |
03 Sep 2022
|
Basant Lal
|
Reverted
|
03 पंजीकरण हेतु अपलोड किये गये अभिलेखों में तकनीकी स्टाफ के रूप में नियुक्त सभी स्टाफ एक ही रख गया है। (फाईल नं0- 44921 भवन कार्य, 44833 सेतु कार्य एवं 44729 मार्ग)
|
59 |
26 Aug 2022
|
Narendra Pant
|
Comments
|
@Basant Lal(010022168) ji, Application has been forwarded to you, kindly do the needfull. comments : महोदय कृपया M/S Prayag Construction द्वारा 03 पंजीकरण हेतु अपलोड किये गये अभिलेखों में तकनीकी स्टाफ के रूप में नियुक्त सभी स्टाफ एक ही रख गया है। (फाईल नं0- 44921 भवन कार्य, 44833 सेतु कार्य एवं 44729 मार्ग) अतः अवलोकनार्थ/आदेशार्थ प्रस्तुत।
|
60 |
28 Jul 2022
|
Narendra Pant
|
Comments
|
महोदय कृपया M/S Prayag Construction द्वारा 03 पंजीकरण हेतु अपलोड किये गये अभिलेखों में तकनीकी स्टाफ के रूप में नियुक्त सभी स्टाफ एक ही रख गया है। (फाईल नं0- 44921 भवन कार्य, 44833 सेतु कार्य एवं 44729 मार्ग) अतः अवलोकनार्थ/आदेशार्थ प्रस्तुत।
|
61 |
22 Jul 2022
|
Yogamber Singh Rawat
|
Comments
|
Application Forwarded to Niyojan 3 Team.
|
62 |
22 Jul 2022
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
63 |
20 Jul 2022
|
Manoj Kumar Bisht
|
Reverted
|
Update your permanent employee list. Mr Laxman Singh negi is not engaged with you
|
64 |
11 Jul 2022
|
Basant Lal
|
Submitted
|
दूरभाष पर वार्तानुसार सम्बन्धित तकनीकी स्टाफ में कार्यरत श्री लक्ष्मण सिंह नेगी द्वारा अवगत कराया गया है कि वे प्रयाग कन्स्टक्शन के साथ कार्य नही करते है।
|
65 |
11 Jul 2022
|
Narendra Pant
|
Submitted
|
सम्बन्धित डिप्लोमाधारी श्री लक्ष्मण सिंह नेगी से दूरभाष पर हुई वार्तानुसार श्री लक्ष्मण सिंह नेगी श्री राम बाहदुर सलामी के साथ कार्यरत है। प्रयाग कन्स्टक्शन के साथ कार्यरत नही है। अतः प्रकरण वापस किया जा सकता है।
|
66 |
02 Jul 2022
|
Manoj Kumar Bisht
|
Submitted
|
Laxman Singh negi is with 2 contractor in application 44921,45898 . Verify this.
|
67 |
01 Jul 2022
|
Narendra Pant
|
In-Process
|
work Conatruction of Stock Man Center Silpata Gairsain has been approved by Narendra Pant
|
68 |
01 Jul 2022
|
Narendra Pant
|
In-Process
|
work Construction of Add Primary Health Center Malsi and Type_1,2nos and Type 2,2nos has been approved by Narendra Pant
|
69 |
01 Jul 2022
|
Narendra Pant
|
In-Process
|
work Vikaskhand Karyalay Bhawan Gairsain Ka Bhawan Nirman Karya has been approved by Narendra Pant
|
70 |
28 Jun 2022
|
Manoj Kumar Bisht
|
Submitted
|
document verification is still pending
|
71 |
27 Jun 2022
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction of Staff Quaters type_1 2 nos and Type 11 1Nos and Approach Road at Gairsain
|
72 |
27 Jun 2022
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Conatruction of Stock Man Center Silpata Gairsain
|
73 |
27 Jun 2022
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction of Add Primary Health Center Malsi and Type_1,2nos and Type 2,2nos
|
74 |
27 Jun 2022
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Vikaskhand Karyalay Bhawan Gairsain Ka Bhawan Nirman Karya
|
75 |
27 Jun 2022
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Paryatak Avas Grah Gairsain ka Nirman
|
76 |
27 Jun 2022
|
Kunwar Singh Aswal
|
Comments
|
S.A.O./H.A- SEND DOCUMENTS FOR VERIFICATION. ALL REQUIRED DOCUMENTS ARE UPLOADED.
|
77 |
23 Jun 2022
|
Narendra Pant
|
Comments
|
वरिष्ठ प्रशासनिक अधिकारी महोदय कृपया उक्त सम्बन्ध में अवगत कराना है कि एस0ओ0पी0 के अनुसार फर्म/ठेकेदार द्वारा अपलोड प्रपत्रों का परीक्षण किया गया है, जिनकी स्थिति निम्नानुसार हैः- 1. एस0ओ0पी0 के क्रमांक 4 के अनुसार फर्म/ठेकेदार द्वारा फोटो अपलोड की गयी है। 2. एस0ओ0पी0 के क्रमांक 5 के अनुसार चरित्र प्रमाण पत्र की प्रति अपलोड की गयी है। 3. एस0ओ0पी0 के क्रमांक 6 के अनुसार हैसियत प्रमाण पत्र के स्थान पर भारतीय स्टैट बैक गैरसैण जिला चमोली के पत्र दिनांक 10.06.2022 द्वारा जारी रू0 23,549.237 लाख की बैक सॉल्वेंसी सर्टिफिकेट की प्रति अपलोड की गयी है। 4. एस0ओ0पी0 के क्रमांक 7 अनुसार फर्म/ठेकेदार द्वारा जी0एस0टी0 प्रमाण पत्र की प्रति अपलोड की गयी है। 6. एस0ओ0पी0 के क्रमांक 9 के अनुसार फर्म/ठेकेदार द्वारा मशीनरी की सूची दी गयी है। 7. एस0ओ0पी0 के क्रमांक 10 के अनुसार फर्म/ठेकेदार द्वारा तकनीकी स्टॉफ के शैक्षिक प्रमाण पत्र अपलोड किये गये है। 8. एस0ओ0पी0 के क्रमांक 11 के अनुसार फर्म/ठेकेदार द्वारा अनुभव प्रमाण पत्र की प्रति अपलोड किये गये है। जिसका सत्यापन किया जाना आपेक्षित है। 9. एस0ओ0पी0 के क्रमांक 12 के अनुसार फर्म/ठेकेदार द्वारा जमानती धनराशि रू0 1.00 (रू0 एक लाख) मात्र का पूर्व में इस कार्यालय में जमा है। जिसका पुनः सम्बन्धित बैंक से सत्यापन किया जाना है। 10. एस0ओ0पी0 के क्रमांक 13 के अनुसार फर्म/ठेकेदार द्वारा वर्ष 2021-22 की आई0टी0आर0 की प्रति अपलोड की गयी है। अतः उपरोक्तानुसार अवलोकनार्थ/ आदेशार्थ प्रस्तुत।
|
78 |
20 Jun 2022
|
Yogamber Singh Rawat
|
Comments
|
Application Forwarded to Niyojan 3 Team.
|
79 |
20 Jun 2022
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|