1 |
27 Feb 2024
|
Kedar Singh
|
Reverted
|
Document not Submitted. Shri Vikas Sharma working with other contractors.
|
2 |
27 Feb 2024
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Hill cutting and construction work of scraper in the remaining part of Garon_kandi_dwargarh motor road under the State Plan in Dhanaulti.
|
3 |
27 Feb 2024
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Under the Honorable Chief Ministers Announcement No. 142/2015, asphalting work of motor road from Sumankyar to Bangaon in Jaunpur Vikaskhand of Dhanaulti assembly constituency of Tehri Garhwal
|
4 |
27 Feb 2024
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Improvement and Reconstruction of hudoli panigaon motor road under State Sector in Purola Block of Distt. Uttarkashi Km 1 to 6
|
5 |
26 Feb 2024
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Hudoli Panigaun to kantari Motor road stage_II (Lenth_ 5.775km)
|
6 |
23 Feb 2024
|
Kedar Singh
|
Reverted
|
Document not Submitted. Shri Vikas Sharma working with other contractors.
|
7 |
21 Feb 2024
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Hudoli Panigaun to kantari Motor road stage_II (Lenth_ 5.775km)
|
8 |
21 Feb 2024
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Hill cutting and construction work of scraper in the remaining part of Garon_kandi_dwargarh motor road under the State Plan in Dhanaulti.
|
9 |
21 Feb 2024
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Under the Honorable Chief Ministers Announcement No. 142/2015, asphalting work of motor road from Sumankyar to Bangaon in Jaunpur Vikaskhand of Dhanaulti assembly constituency of Tehri Garhwal
|
10 |
21 Feb 2024
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Improvement and Reconstruction of hudoli panigaon motor road under State Sector in Purola Block of Distt. Uttarkashi Km 1 to 6
|
11 |
21 Feb 2024
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Conversion of submergence road upto chittad LVR in to motor road hill side cutting in km 32
|
12 |
15 Feb 2024
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Hudoli Panigaun to kantari Motor road stage_II (Lenth_ 5.775km)
|
13 |
15 Feb 2024
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Hill cutting and construction work of scraper in the remaining part of Garon_kandi_dwargarh motor road under the State Plan in Dhanaulti.
|
14 |
15 Feb 2024
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Under the Honorable Chief Ministers Announcement No. 142/2015, asphalting work of motor road from Sumankyar to Bangaon in Jaunpur Vikaskhand of Dhanaulti assembly constituency of Tehri Garhwal
|
15 |
15 Feb 2024
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Improvement and Reconstruction of hudoli panigaon motor road under State Sector in Purola Block of Distt. Uttarkashi Km 1 to 6
|
16 |
15 Feb 2024
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Conversion of submergence road upto chittad LVR in to motor road hill side cutting in km 32
|
17 |
15 Feb 2024
|
Manoj Barthwal
|
Comments
|
Application Forwarded to Parkeen Team.
|
18 |
15 Feb 2024
|
Manoj Barthwal
|
Acknowledged
|
Application Acknoledged.
|