1 |
05 Mar 2024
|
Om Prakash
|
Registration Granted
|
Approved as per comments of officer and the section.
|
2 |
02 Mar 2024
|
Jeewan Singh Hyanki
|
In-Process
|
@Om Prakash(010099553) ji, Application has been forwarded to you, kindly do the needfull. comments : विभाग में ठेकेदारों की सूची श्रेणी ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत
|
3 |
02 Mar 2024
|
Vinod Kumar
|
In-Process
|
@Jeewan Singh Hyanki(010099561) ji, Application has been forwarded to you, kindly do the needfull. comments : SSO Sir, विभाग में ठेकेदारों की सूची श्रेणी ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत
|
4 |
02 Mar 2024
|
Kedar Singh
|
In-Process
|
@Vinod Kumar(570064276) ji, Application has been forwarded to you, kindly do the needfull. comments : EE Sir, ठेकेदार द्वारा कमियो का निराकरण कर दिया गया है अतः विभाग में ठेकेदारों की सूची श्रेणी ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत
|
5 |
02 Mar 2024
|
Yogamber Singh Rawat
|
In-Process
|
Application Forwarded to Parkeen Team.
|
6 |
02 Mar 2024
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
7 |
02 Mar 2024
|
Vinod Kumar
|
Reverted
|
Technical Staff Shri Sachin kumar Aadhaar Card not match.
|
8 |
01 Mar 2024
|
Kedar Singh
|
In-Process
|
@Vinod Kumar(570064276) ji, Application has been forwarded to you, kindly do the needfull. comments : EE Sir, ठेकेदार द्वारा कमियो का निराकरण कर दिया गया है अतः विभाग में ठेकेदारों की सूची श्रेणी ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत
|
9 |
01 Mar 2024
|
Yogamber Singh Rawat
|
In-Process
|
Application Forwarded to Parkeen Team.
|
10 |
01 Mar 2024
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
11 |
24 Feb 2024
|
Kedar Singh
|
Reverted
|
the profession mentioned in character certificate and affidavit by employer for technical personnel are contradictory. get it rectified.
|
12 |
17 Feb 2024
|
Jeewan Singh Hyanki
|
In-Process
|
@Anand Singh Manral(010091895) ji, Application has been forwarded to you, kindly do the needfull. comments : the profession mentioned in character certificate and affidavit by employer for technical personnel are contradictory. get it rectified.
|
13 |
17 Feb 2024
|
Jeewan Singh Hyanki
|
In-Process
|
@Om Prakash(010099553) ji, Application has been forwarded to you, kindly do the needfull. comments : विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत
|
14 |
01 Feb 2024
|
Vinod Kumar
|
In-Process
|
@Jeewan Singh Hyanki(010099561) ji, Application has been forwarded to you, kindly do the needfull. comments : SSO Sir, विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत
|
15 |
31 Jan 2024
|
Kedar Singh
|
In-Process
|
@Vinod Kumar(570064276) ji, Application has been forwarded to you, kindly do the needfull. comments : EE Sir, सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत
|
16 |
29 Jan 2024
|
Yogamber Singh Rawat
|
In-Process
|
Application Forwarded to Parkeen Team.
|
17 |
29 Jan 2024
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
18 |
24 Jan 2024
|
Kedar Singh
|
Reverted
|
Please upload technical staff document.
|
19 |
20 Jan 2024
|
Kedar Singh
|
In-Process
|
work Under the state plan 2021_22, construction by interlocking tiles from salims house towards jyotipal house in village Bandarjut of Jwalapur assembly constituency of Haridwar district work has been approved by Kedar Singh
|
20 |
20 Jan 2024
|
Kedar Singh
|
In-Process
|
work Under the State Plan 2021_22 of Haridwar district construction work through interlocking tiles on the main road from Ravidas Temple to the government tube well in village Rasulpur Tongian has been approved by Kedar Singh
|
21 |
20 Jan 2024
|
Kedar Singh
|
In-Process
|
work Under the State Plan 2021_22, construction of Haridwar work through interlocking tiles on the main road leading from Shiv Temple to Rasulpur in village Teliwala of Jwalapur has been approved by Kedar Singh
|
22 |
20 Jan 2024
|
Kedar Singh
|
In-Process
|
work Under the State Plan 2021_22, construction work of the road from Dhariwala to badshahpur of Haridwar Rural, Haridwar has been approved by Kedar Singh
|
23 |
20 Jan 2024
|
Kedar Singh
|
In-Process
|
work Under the state plan 2021_22, construction work of interlocking tiles and drain construction of the road leading from siddarth enclave of BHEL raipur to khalsa colony in Haridwar district. has been approved by Kedar Singh
|
24 |
09 Jan 2024
|
Mahendra Kumar
|
In-Process
|
Mail Has been send for Verification of work Under the state plan 2021_22, construction by interlocking tiles from salims house towards jyotipal house in village Bandarjut of Jwalapur assembly constituency of Haridwar district work
|
25 |
09 Jan 2024
|
Mahendra Kumar
|
In-Process
|
Mail Has been send for Verification of work Under the State Plan 2021_22 of Haridwar district construction work through interlocking tiles on the main road from Ravidas Temple to the government tube well in village Rasulpur Tongian
|
26 |
09 Jan 2024
|
Mahendra Kumar
|
In-Process
|
Mail Has been send for Verification of work Under the State Plan 2021_22, construction of Haridwar work through interlocking tiles on the main road leading from Shiv Temple to Rasulpur in village Teliwala of Jwalapur
|
27 |
09 Jan 2024
|
Mahendra Kumar
|
In-Process
|
Mail Has been send for Verification of work Under the State Plan 2021_22, construction work of the road from Dhariwala to badshahpur of Haridwar Rural, Haridwar
|
28 |
09 Jan 2024
|
Mahendra Kumar
|
In-Process
|
Mail Has been send for Verification of work Under the state plan 2021_22, construction work of interlocking tiles and drain construction of the road leading from siddarth enclave of BHEL raipur to khalsa colony in Haridwar district.
|
29 |
09 Jan 2024
|
Yogamber Singh Rawat
|
Comments
|
Application Forwarded to Parkeen Team.
|
30 |
09 Jan 2024
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|