1 |
18 Mar 2024
|
Om Prakash
|
Registration Granted
|
Approved as per comment of officer dated 11.03.2024
|
2 |
11 Mar 2024
|
Manoj Kumar Bisht
|
In-Process
|
@Om Prakash(010099553) ji, Application has been forwarded to you, kindly do the needfull. comments : Sir, Registration may be granted
|
3 |
28 Feb 2024
|
Deepak Kumar
|
In-Process
|
@Manoj Kumar Bisht(010096004) ji, Application has been forwarded to you, kindly do the needfull. comments : महोदय ठेकेदार/फर्म द्वारा अपलोड किये गये अभिलेखों का सत्यापन प्राप्त हो चुका है। अतः पंजीकरण हेतु विचार करना चाहें।
|
4 |
14 Feb 2024
|
Basant Lal
|
In-Process
|
@Deepak Kumar(42009820) ji, Application has been forwarded to you, kindly do the needfull. comments : , कृपया ठेकेदार/फर्म द्वारा अपलोड किये गये अभिलेखों में अनुभव प्रमाण पत्र एवं बैंक सैल्वेसी प्रमाण पत्र का सत्यापन प्राप्त हो चुका है। अतः पंजीकरण हेतु विचार करना चाहें।
|
5 |
12 Feb 2024
|
Narendra Pant
|
In-Process
|
@Basant Lal(010022168) ji, Application has been forwarded to you, kindly do the needfull. comments : वरिष्ठ प्रशासनिक अधिकारी महोदय, कृपया ठेकेदार/फर्म द्वारा अपलोड किये गये अभिलेखों में अनुभव प्रमाण पत्र एवं बैंक सैल्वेसी प्रमाण पत्र का सत्यापन प्राप्त हो चुका है। अतः पंजीकरण हेतु विचार करना चाहें।
|
6 |
12 Feb 2024
|
Narendra Pant
|
In-Process
|
work Construction and maintenance of 18mtr. span steel truss bridge at Gorpa Sirwadi_Kurchola in km. 9 & construction and maintenance of 48 mtr. span steel truss bridge at Gorpa Sirwadi_Kurchola in km. 4 has been approved by Narendra Pant
|
7 |
12 Feb 2024
|
Narendra Pant
|
In-Process
|
work 30 mtr. span steel girder bridge over Hilau Gaad at km 0.750 of Tuneta to Bharanga MR. has been approved by Narendra Pant
|
8 |
12 Jan 2024
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction and maintenance of 18mtr. span steel truss bridge at Gorpa Sirwadi_Kurchola in km. 9 & construction and maintenance of 48 mtr. span steel truss bridge at Gorpa Sirwadi_Kurchola in km. 4
|
9 |
12 Jan 2024
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work 30 mtr. span steel girder bridge over Hilau Gaad at km 0.750 of Tuneta to Bharanga MR.
|
10 |
29 Dec 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction and maintenance of 18mtr. span steel truss bridge at Gorpa Sirwadi_Kurchola in km. 9 & construction and maintenance of 48 mtr. span steel truss bridge at Gorpa Sirwadi_Kurchola in km. 4
|
11 |
29 Dec 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work 30 mtr. span steel girder bridge over Hilau Gaad at km 0.750 of Tuneta to Bharanga MR.
|
12 |
29 Dec 2023
|
Narendra Pant
|
In-Process
|
work Work of 30 mtr, steel girder in km. 4 of Lasi Sartoli motor road under Pradhan Mantri Gram Sadak Yojna has been approved by Narendra Pant
|
13 |
29 Dec 2023
|
Narendra Pant
|
In-Process
|
work Work of 30 mtr, steel girder in km. 5 of Lasi Sartoli motor road under Pradhan Mantri Gram Sadak Yojna has been approved by Narendra Pant
|
14 |
29 Dec 2023
|
Narendra Pant
|
In-Process
|
work Construction of motor bridge near Tilwara Bhardar Sorakhal motor road km. 27 HM 8_10 under district plan. has been approved by Narendra Pant
|
15 |
28 Dec 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction of motor bridge near Tilwara Bhardar Sorakhal motor road km. 27 HM 8_10 under district plan.
|
16 |
16 Dec 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction and maintenance of 18mtr. span steel truss bridge at Gorpa Sirwadi_Kurchola in km. 9 & construction and maintenance of 48 mtr. span steel truss bridge at Gorpa Sirwadi_Kurchola in km. 4
|
17 |
16 Dec 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work 30 mtr. span steel girder bridge over Hilau Gaad at km 0.750 of Tuneta to Bharanga MR.
|
18 |
16 Dec 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction of motor bridge near Tilwara Bhardar Sorakhal motor road km. 27 HM 8_10 under district plan.
|
19 |
20 Nov 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work 30 mtr. span steel girder bridge over Hilau Gaad at km 0.750 of Tuneta to Bharanga MR.
|
20 |
20 Nov 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction of motor bridge near Tilwara Bhardar Sorakhal motor road km. 27 HM 8_10 under district plan.
|
21 |
20 Nov 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction and maintenance of 18mtr. span steel truss bridge at Gorpa Sirwadi_Kurchola in km. 9 & construction and maintenance of 48 mtr. span steel truss bridge at Gorpa Sirwadi_Kurchola in km. 4
|
22 |
10 Nov 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction and maintenance of 18mtr. span steel truss bridge at Gorpa Sirwadi_Kurchola in km. 9 & construction and maintenance of 48 mtr. span steel truss bridge at Gorpa Sirwadi_Kurchola in km. 4
|
23 |
10 Nov 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work 30 mtr. span steel girder bridge over Hilau Gaad at km 0.750 of Tuneta to Bharanga MR.
|
24 |
10 Nov 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction of motor bridge near Tilwara Bhardar Sorakhal motor road km. 27 HM 8_10 under district plan.
|
25 |
26 Oct 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Work of 30 mtr, steel girder in km. 4 of Lasi Sartoli motor road under Pradhan Mantri Gram Sadak Yojna
|
26 |
26 Oct 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Work of 30 mtr, steel girder in km. 5 of Lasi Sartoli motor road under Pradhan Mantri Gram Sadak Yojna
|
27 |
26 Oct 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction and maintenance of 18mtr. span steel truss bridge at Gorpa Sirwadi_Kurchola in km. 9 & construction and maintenance of 48 mtr. span steel truss bridge at Gorpa Sirwadi_Kurchola in km. 4
|
28 |
26 Oct 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work 30 mtr. span steel girder bridge over Hilau Gaad at km 0.750 of Tuneta to Bharanga MR.
|
29 |
26 Oct 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction of motor bridge near Tilwara Bhardar Sorakhal motor road km. 27 HM 8_10 under district plan.
|
30 |
20 Oct 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Work of 30 mtr, steel girder in km. 4 of Lasi Sartoli motor road under Pradhan Mantri Gram Sadak Yojna
|
31 |
20 Oct 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Work of 30 mtr, steel girder in km. 5 of Lasi Sartoli motor road under Pradhan Mantri Gram Sadak Yojna
|
32 |
20 Oct 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction and maintenance of 18mtr. span steel truss bridge at Gorpa Sirwadi_Kurchola in km. 9 & construction and maintenance of 48 mtr. span steel truss bridge at Gorpa Sirwadi_Kurchola in km. 4
|
33 |
20 Oct 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work 30 mtr. span steel girder bridge over Hilau Gaad at km 0.750 of Tuneta to Bharanga MR.
|
34 |
20 Oct 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction of motor bridge near Tilwara Bhardar Sorakhal motor road km. 27 HM 8_10 under district plan.
|
35 |
26 Sep 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Work of 30 mtr, steel girder in km. 5 of Lasi Sartoli motor road under Pradhan Mantri Gram Sadak Yojna
|
36 |
26 Sep 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Work of 30 mtr, steel girder in km. 4 of Lasi Sartoli motor road under Pradhan Mantri Gram Sadak Yojna
|
37 |
26 Sep 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction and maintenance of 18mtr. span steel truss bridge at Gorpa Sirwadi_Kurchola in km. 9 & construction and maintenance of 48 mtr. span steel truss bridge at Gorpa Sirwadi_Kurchola in km. 4
|
38 |
26 Sep 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work 30 mtr. span steel girder bridge over Hilau Gaad at km 0.750 of Tuneta to Bharanga MR.
|
39 |
26 Sep 2023
|
Narendra Pant
|
In-Process
|
Mail Has been send for Verification of work Construction of motor bridge near Tilwara Bhardar Sorakhal motor road km. 27 HM 8_10 under district plan.
|
40 |
15 Sep 2023
|
Yogamber Singh Rawat
|
Comments
|
Application Forwarded to Niyojan 3 Team.
|
41 |
15 Sep 2023
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
42 |
15 Sep 2023
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|