Dashboard Contractor Registration

Contractor Application No. 73177 for Category Road Class A Applied Office : E-n-C Office Applied On Date : 07 Aug 2023

19 Aug 2023

Status : Registration Granted

By: Dayanand

Approved.

09 Aug 2023

Status : In-Process

By: Kedar Singh

@Jeewan Singh Hyanki(010099561) ji, Application has been forwarded to you, kindly do the needfull. comments : SSO Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत

09 Aug 2023

Status : In-Process

By: Kedar Singh

work CC road construction work from Vikasnagar main road to Tehsil office. has been approved by Kedar Singh

09 Aug 2023

Status : In-Process

By: Kedar Singh

work Tiles Road construction work from Ranveer Chauhan to KS house in Rasulpur Vikasnagar has been approved by Kedar Singh

09 Aug 2023

Status : In-Process

By: Kedar Singh

work Road Construction work from Langha road Pulia to Vikram Tomar house in Dhakowala Vikasnagar has been approved by Kedar Singh

09 Aug 2023

Status : In-Process

By: Kedar Singh

work Road Construction work from the main road to Mr. Suratram Sharma house and from block road to Mr Hari Singh (NH_123)) on Bhimawala Road located in Babugarh under Development block Vikasnagar. has been approved by Kedar Singh

09 Aug 2023

Status : In-Process

By: Kedar Singh

work Construction work of various road in gram sabha Jollygrant under Block Doiwala.1 Road Construction work from M/s Green Blue resturant to Mr. Surat Singh Rawat house. 2. Main road in Adarsh nagar lane no. 12 (HIHT to Jolly) Mr. Dharmanand Bhatt & road construction work up to Mr./Ms. Bohra....etc has been approved by Kedar Singh

07 Aug 2023

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work Road Construction work from Langha road Pulia to Vikram Tomar house in Dhakowala Vikasnagar

07 Aug 2023

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work Road Construction work from the main road to Mr. Suratram Sharma house and from block road to Mr Hari Singh (NH_123)) on Bhimawala Road located in Babugarh under Development block Vikasnagar.

07 Aug 2023

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work Construction work of various road in gram sabha Jollygrant under Block Doiwala.1 Road Construction work from M/s Green Blue resturant to Mr. Surat Singh Rawat house. 2. Main road in Adarsh nagar lane no. 12 (HIHT to Jolly) Mr. Dharmanand Bhatt & road construction work up to Mr./Ms. Bohra....etc

07 Aug 2023

Status : Acknowledged

By: Yogamber Singh Rawat

Application Forwarded to Parkeen Team.

07 Aug 2023

Status : Acknowledged

By: Yogamber Singh Rawat

Application Acknoledged.

07 Aug 2023

Status : Reverted

By: Kedar Singh

MDDA Email Id is not correct.

01 Aug 2023

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work CC road construction work from Vikasnagar main road to Tehsil office.

01 Aug 2023

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work Tiles Road construction work from Ranveer Chauhan to KS house in Rasulpur Vikasnagar

01 Aug 2023

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work Road Construction work from Langha road Pulia to Vikram Tomar house in Dhakowala Vikasnagar

01 Aug 2023

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work Road Construction work from the main road to Mr. Suratram Sharma house and from block road to Mr Hari Singh (NH_123)) on Bhimawala Road located in Babugarh under Development block Vikasnagar.

01 Aug 2023

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work Construction work of various road in gram sabha Jollygrant under Block Doiwala.1 Road Construction work from M/s Green Blue resturant to Mr. Surat Singh Rawat house. 2. Main road in Adarsh nagar lane no. 12 (HIHT to Jolly) Mr. Dharmanand Bhatt & road construction work up to Mr./Ms. Bohra....etc

01 Aug 2023

Status : Comments

By: Yogamber Singh Rawat

Application Forwarded to Parkeen Team.

01 Aug 2023

Status : Acknowledged

By: Yogamber Singh Rawat

Application Acknoledged.

27 Jul 2023

Status : Reverted

By: Kedar Singh

Aswani Kumar Mainwal working with other contractor.

27 Jul 2023

Status : Comments

By: Yogamber Singh Rawat

Application Forwarded to Parkeen Team.

27 Jul 2023

Status : Acknowledged

By: Yogamber Singh Rawat

Application Acknoledged.


Sl No On Date Officer Status Remarks
1 19 Aug 2023 Dayanand Registration Granted Approved.
2 09 Aug 2023 Kedar Singh In-Process @Jeewan Singh Hyanki(010099561) ji, Application has been forwarded to you, kindly do the needfull. comments : SSO Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत
3 09 Aug 2023 Kedar Singh In-Process work CC road construction work from Vikasnagar main road to Tehsil office. has been approved by Kedar Singh
4 09 Aug 2023 Kedar Singh In-Process work Tiles Road construction work from Ranveer Chauhan to KS house in Rasulpur Vikasnagar has been approved by Kedar Singh
5 09 Aug 2023 Kedar Singh In-Process work Road Construction work from Langha road Pulia to Vikram Tomar house in Dhakowala Vikasnagar has been approved by Kedar Singh
6 09 Aug 2023 Kedar Singh In-Process work Road Construction work from the main road to Mr. Suratram Sharma house and from block road to Mr Hari Singh (NH_123)) on Bhimawala Road located in Babugarh under Development block Vikasnagar. has been approved by Kedar Singh
7 09 Aug 2023 Kedar Singh In-Process work Construction work of various road in gram sabha Jollygrant under Block Doiwala.1 Road Construction work from M/s Green Blue resturant to Mr. Surat Singh Rawat house. 2. Main road in Adarsh nagar lane no. 12 (HIHT to Jolly) Mr. Dharmanand Bhatt & road construction work up to Mr./Ms. Bohra....etc has been approved by Kedar Singh
8 07 Aug 2023 Kedar Singh In-Process Mail Has been send for Verification of work Road Construction work from Langha road Pulia to Vikram Tomar house in Dhakowala Vikasnagar
9 07 Aug 2023 Kedar Singh In-Process Mail Has been send for Verification of work Road Construction work from the main road to Mr. Suratram Sharma house and from block road to Mr Hari Singh (NH_123)) on Bhimawala Road located in Babugarh under Development block Vikasnagar.
10 07 Aug 2023 Kedar Singh In-Process Mail Has been send for Verification of work Construction work of various road in gram sabha Jollygrant under Block Doiwala.1 Road Construction work from M/s Green Blue resturant to Mr. Surat Singh Rawat house. 2. Main road in Adarsh nagar lane no. 12 (HIHT to Jolly) Mr. Dharmanand Bhatt & road construction work up to Mr./Ms. Bohra....etc
11 07 Aug 2023 Yogamber Singh Rawat Acknowledged Application Forwarded to Parkeen Team.
12 07 Aug 2023 Yogamber Singh Rawat Acknowledged Application Acknoledged.
13 07 Aug 2023 Kedar Singh Reverted MDDA Email Id is not correct.
14 01 Aug 2023 Kedar Singh In-Process Mail Has been send for Verification of work CC road construction work from Vikasnagar main road to Tehsil office.
15 01 Aug 2023 Kedar Singh In-Process Mail Has been send for Verification of work Tiles Road construction work from Ranveer Chauhan to KS house in Rasulpur Vikasnagar
16 01 Aug 2023 Kedar Singh In-Process Mail Has been send for Verification of work Road Construction work from Langha road Pulia to Vikram Tomar house in Dhakowala Vikasnagar
17 01 Aug 2023 Kedar Singh In-Process Mail Has been send for Verification of work Road Construction work from the main road to Mr. Suratram Sharma house and from block road to Mr Hari Singh (NH_123)) on Bhimawala Road located in Babugarh under Development block Vikasnagar.
18 01 Aug 2023 Kedar Singh In-Process Mail Has been send for Verification of work Construction work of various road in gram sabha Jollygrant under Block Doiwala.1 Road Construction work from M/s Green Blue resturant to Mr. Surat Singh Rawat house. 2. Main road in Adarsh nagar lane no. 12 (HIHT to Jolly) Mr. Dharmanand Bhatt & road construction work up to Mr./Ms. Bohra....etc
19 01 Aug 2023 Yogamber Singh Rawat Comments Application Forwarded to Parkeen Team.
20 01 Aug 2023 Yogamber Singh Rawat Acknowledged Application Acknoledged.
21 27 Jul 2023 Kedar Singh Reverted Aswani Kumar Mainwal working with other contractor.
22 27 Jul 2023 Yogamber Singh Rawat Comments Application Forwarded to Parkeen Team.
23 27 Jul 2023 Yogamber Singh Rawat Acknowledged Application Acknoledged.