Contractor Application No. 71327 for Category Road Class A Applied Office : E-n-C Office Applied On Date : 29 Jun 2023

10 Jul 2023

Status : Registration Granted

By: Girish Chandra Arya

Approved as per approval, verification and recommendation of concern officers and employees.

10 Jul 2023

Status : In-Process

By: Prem Singh Nabiyal

@Girish Chandra Arya(010099552) ji, Application has been forwarded to you, kindly do the needfull. comments : As per the recommendation of EE the approval for registration on Road class A be accorded please

06 Jul 2023

Status : In-Process

By: Balram Misra

@Prem Singh Nabiyal(570068221) ji, Application has been forwarded to you, kindly do the needfull. comments : Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत।

05 Jul 2023

Status : In-Process

By: Kedar Singh

@Balram Misra(420010048) ji, Application has been forwarded to you, kindly do the needfull. comments : EE Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत।

05 Jul 2023

Status : In-Process

By: Kedar Singh

work construction work of road in village Badwala has been approved by Kedar Singh

05 Jul 2023

Status : In-Process

By: Kedar Singh

work Construction work of road from inder singhs house to darshan lal house in devthala village of vikasnagar has been approved by Kedar Singh

05 Jul 2023

Status : In-Process

By: Kedar Singh

work construction work of roads from lakdwad road in badwala to village rajawala has been approved by Kedar Singh

05 Jul 2023

Status : In-Process

By: Kedar Singh

work Reconstruction and improvement work of barwala_dumet_hadowala road under development block of dehradun district has been approved by Kedar Singh

05 Jul 2023

Status : In-Process

By: Kedar Singh

work Protection work from km 189.00 to 243.00 on NH 309 in the state of Uttarakhand has been approved by Kedar Singh

30 Jun 2023

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work construction work of road in village Badwala

30 Jun 2023

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work Construction work of road from inder singhs house to darshan lal house in devthala village of vikasnagar

30 Jun 2023

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work construction work of roads from lakdwad road in badwala to village rajawala

30 Jun 2023

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work Reconstruction and improvement work of barwala_dumet_hadowala road under development block of dehradun district

30 Jun 2023

Status : In-Process

By: Kedar Singh

Mail Has been send for Verification of work Protection work from km 189.00 to 243.00 on NH 309 in the state of Uttarakhand

30 Jun 2023

Status : Comments

By: Yogamber Singh Rawat

Application Forwarded to Parkeen Team.

30 Jun 2023

Status : Acknowledged

By: Yogamber Singh Rawat

Application Acknoledged.


Sl No On Date Officer Status Remarks
1 10 Jul 2023 Girish Chandra Arya Registration Granted Approved as per approval, verification and recommendation of concern officers and employees.
2 10 Jul 2023 Prem Singh Nabiyal In-Process @Girish Chandra Arya(010099552) ji, Application has been forwarded to you, kindly do the needfull. comments : As per the recommendation of EE the approval for registration on Road class A be accorded please
3 06 Jul 2023 Balram Misra In-Process @Prem Singh Nabiyal(570068221) ji, Application has been forwarded to you, kindly do the needfull. comments : Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत।
4 05 Jul 2023 Kedar Singh In-Process @Balram Misra(420010048) ji, Application has been forwarded to you, kindly do the needfull. comments : EE Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत।
5 05 Jul 2023 Kedar Singh In-Process work construction work of road in village Badwala has been approved by Kedar Singh
6 05 Jul 2023 Kedar Singh In-Process work Construction work of road from inder singhs house to darshan lal house in devthala village of vikasnagar has been approved by Kedar Singh
7 05 Jul 2023 Kedar Singh In-Process work construction work of roads from lakdwad road in badwala to village rajawala has been approved by Kedar Singh
8 05 Jul 2023 Kedar Singh In-Process work Reconstruction and improvement work of barwala_dumet_hadowala road under development block of dehradun district has been approved by Kedar Singh
9 05 Jul 2023 Kedar Singh In-Process work Protection work from km 189.00 to 243.00 on NH 309 in the state of Uttarakhand has been approved by Kedar Singh
10 30 Jun 2023 Kedar Singh In-Process Mail Has been send for Verification of work construction work of road in village Badwala
11 30 Jun 2023 Kedar Singh In-Process Mail Has been send for Verification of work Construction work of road from inder singhs house to darshan lal house in devthala village of vikasnagar
12 30 Jun 2023 Kedar Singh In-Process Mail Has been send for Verification of work construction work of roads from lakdwad road in badwala to village rajawala
13 30 Jun 2023 Kedar Singh In-Process Mail Has been send for Verification of work Reconstruction and improvement work of barwala_dumet_hadowala road under development block of dehradun district
14 30 Jun 2023 Kedar Singh In-Process Mail Has been send for Verification of work Protection work from km 189.00 to 243.00 on NH 309 in the state of Uttarakhand
15 30 Jun 2023 Yogamber Singh Rawat Comments Application Forwarded to Parkeen Team.
16 30 Jun 2023 Yogamber Singh Rawat Acknowledged Application Acknoledged.