1 |
16 Oct 2023
|
Gopal Singh Manral
|
Reverted
|
श्री गणेश दत्त पन्त मै0 सुपर कन्ट्रक्शन में भी पार्टनर है। एस0ओ0पी0 के अनुसार मान्य नहीं है।
|
2 |
14 Oct 2023
|
Navneet Pandey
|
In-Process
|
@Gopal Singh Manral(370021335) ji, Application has been forwarded to you, kindly do the needfull. comments : Person has two registration shown in adhar. check in light of declaration 2nd row for its approprateness
|
3 |
11 Oct 2023
|
Gopal Singh Manral
|
In-Process
|
@Navneet Pandey(020088889426) ji, Application has been forwarded to you, kindly do the needfull. comments : अधिशासी अभियनता महोदय, ठेकेदार द्वारा प्रस्तुत अभिलेखों का सत्यापन प्राप्त हो चुका है। अतः ठेकेदार का मार्ग कार्य श्रेणी ए में पंजीकरण पर विचार करना चाहें। ठेकेदार द्वारा तकनीकी स्टाफ के शपथ पत्र एवं पे-स्लीप मेमोरन्डम आफ अन्डरस्टेडिंग में अपलोड किये गये है।
|
4 |
10 Oct 2023
|
Gopal Singh Manral
|
In-Process
|
@Aasutosh Kumar(61004796) ji, Application has been forwarded to you, kindly do the needfull. comments : अधिशासी अभियनता महोदय,
ठेकेदार द्वारा प्रस्तुत अभिलेखों का सत्यापन प्राप्त हो चुका है। अतः ठेकेदार का मार्ग कार्य श्रेणी ए में पंजीकरण पर विचार करना चाहें। ठेकेदार द्वारा तकनीकी स्टाफ के शपथ पत्र एवं पे-स्लीप मेमोरन्डम आफ अन्डरस्टेडिंग में अपलोड किये गये है।
|
5 |
10 Oct 2023
|
Gopal Singh Manral
|
In-Process
|
work Devipura Saur Km. 13 to Badli Motor Road Stage_I has been approved by Gopal Singh Manral
|
6 |
30 Sep 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Devipura Saur Km. 13 to Badli Motor Road Stage_I
|
7 |
29 Sep 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Devipura Saur Km. 13 to Badli Motor Road Stage_I
|
8 |
29 Sep 2023
|
Gopal Singh Manral
|
In-Process
|
work Devipura Saur Km. 13 to Badli Motor Road Stage_I has been dis-approved by Gopal Singh Manral
|
9 |
29 Sep 2023
|
Gopal Singh Manral
|
In-Process
|
work Construction of Bans Pathan Pul to Choura Golthi Motor Road Stage_1 has been approved by Gopal Singh Manral
|
10 |
29 Sep 2023
|
Gopal Singh Manral
|
In-Process
|
work Reconstruction of Kathpuriya to Kurchon Motor Road has been approved by Gopal Singh Manral
|
11 |
29 Sep 2023
|
Gopal Singh Manral
|
In-Process
|
work Reconstruction of Ghughukhan to Saur Motor Road in District Nainital has been approved by Gopal Singh Manral
|
12 |
29 Sep 2023
|
Gopal Singh Manral
|
In-Process
|
work Reconstruction & Improvement of Kasiyalekh _ Harinagar_Kafali_M/R To Chila Motor road has been approved by Gopal Singh Manral
|
13 |
27 Sep 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
14 |
21 Sep 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
15 |
11 Sep 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
16 |
06 Sep 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
17 |
04 Sep 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
18 |
23 Aug 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
19 |
21 Aug 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
20 |
11 Aug 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
21 |
11 Aug 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
22 |
09 Aug 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
23 |
05 Aug 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
24 |
31 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
25 |
31 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
26 |
28 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
27 |
28 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
28 |
28 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
29 |
24 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction & Improvement of Kasiyalekh _ Harinagar_Kafali_M/R To Chila Motor road
|
30 |
24 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
31 |
19 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction & Improvement of Kasiyalekh _ Harinagar_Kafali_M/R To Chila Motor road
|
32 |
19 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Ghughukhan to Saur Motor Road in District Nainital
|
33 |
19 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
34 |
18 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction & Improvement of Kasiyalekh _ Harinagar_Kafali_M/R To Chila Motor road
|
35 |
18 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Ghughukhan to Saur Motor Road in District Nainital
|
36 |
18 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
37 |
12 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction & Improvement of Kasiyalekh _ Harinagar_Kafali_M/R To Chila Motor road
|
38 |
12 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Ghughukhan to Saur Motor Road in District Nainital
|
39 |
12 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
40 |
11 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction & Improvement of Kasiyalekh _ Harinagar_Kafali_M/R To Chila Motor road
|
41 |
11 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Ghughukhan to Saur Motor Road in District Nainital
|
42 |
11 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
43 |
05 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction & Improvement of Kasiyalekh _ Harinagar_Kafali_M/R To Chila Motor road
|
44 |
05 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Ghughukhan to Saur Motor Road in District Nainital
|
45 |
05 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
46 |
05 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Construction of Bans Pathan Pul to Choura Golthi Motor Road Stage_1
|
47 |
05 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Devipura Saur Km. 13 to Badli Motor Road Stage_I
|
48 |
04 Jul 2023
|
Manoj Barthwal
|
Submitted
|
Application Forwarded to RTI Team.
|
49 |
04 Jul 2023
|
Manoj Barthwal
|
Acknowledged
|
Application Acknoledged.
|
50 |
02 Jul 2023
|
Gopal Singh Manral
|
Reverted
|
आप द्वारा प्रस्तुत डिग्री होल्डर श्री गिरीश चन्द्र जो मै0 टी0डी0 पलडिया के साथ भी कार्यरत है मान्य नहीं है।
|
51 |
02 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction & Improvement of Kasiyalekh _ Harinagar_Kafali_M/R To Chila Motor road
|
52 |
02 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Ghughukhan to Saur Motor Road in District Nainital
|
53 |
02 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Reconstruction of Kathpuriya to Kurchon Motor Road
|
54 |
02 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Construction of Bans Pathan Pul to Choura Golthi Motor Road Stage_1
|
55 |
02 Jul 2023
|
Gopal Singh Manral
|
In-Process
|
Mail Has been send for Verification of work Devipura Saur Km. 13 to Badli Motor Road Stage_I
|
56 |
01 Jul 2023
|
Yogamber Singh Rawat
|
Comments
|
Application Forwarded to RTI Team.
|
57 |
01 Jul 2023
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|