Contractor Application No. 69302 for Category Electrical Class A Applied Office : E-n-C Office Applied On Date : 17 Jun 2023

10 Jul 2023

Status : Registration Granted

By: Girish Chandra Arya

Approved as per approval, verification and recommendation of concern officers and employees.

10 Jul 2023

Status : In-Process

By: Prem Singh Nabiyal

@Girish Chandra Arya(010099552) ji, Application has been forwarded to you, kindly do the needfull. comments : As per the recommendation of EE the approval for registration in Electrical Class A category may be accorded

28 Jun 2023

Status : In-Process

By: Balram Misra

@Prem Singh Nabiyal(570068221) ji, Application has been forwarded to you, kindly do the needfull. comments : ठेकेदार द्वारा प्रस्तुत अभिलेखों का सत्यापन प्राप्त हो चुका है। अतः ठेकेदार का विद्युत कार्य श्रेणी ए में पंजीकरण के नवीनीकरण पर विचार करना चाहें।

22 Jun 2023

Status : In-Process

By: Gopal Singh Manral

@Balram Misra(420010048) ji, Application has been forwarded to you, kindly do the needfull. comments : ठेकेदार द्वारा प्रस्तुत अभिलेखों का सत्यापन प्राप्त हो चुका है। अतः ठेकेदार का विद्युत कार्य श्रेणी ए में पंजीकरण के नवीनीकरण पर विचार करना चाहें।

22 Jun 2023

Status : In-Process

By: Gopal Singh Manral

work Internal Electrification work has been approved by Gopal Singh Manral

22 Jun 2023

Status : In-Process

By: Gopal Singh Manral

work Internal Electrification work in Revenue Colony has been approved by Gopal Singh Manral

22 Jun 2023

Status : In-Process

By: Gopal Singh Manral

work Internal Electrification work has been approved by Gopal Singh Manral

22 Jun 2023

Status : In-Process

By: Gopal Singh Manral

work Internal Electrification work has been approved by Gopal Singh Manral

22 Jun 2023

Status : In-Process

By: Gopal Singh Manral

work Internal work In kasturba Gandhi girl child school has been approved by Gopal Singh Manral

21 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Internal Electrification work

21 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Internal Electrification work

21 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Internal Electrification work

21 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Internal Electrification work

21 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Internal Electrification work

21 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Internal Electrification work

21 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Internal Electrification work

21 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Internal work In kasturba Gandhi girl child school

21 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Internal Electrification work

21 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Internal Electrification work

21 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Internal Electrification work in Revenue Colony

21 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Internal Electrification work

20 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Internal Electrification work

20 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Internal Electrification work

20 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Internal Electrification work in Revenue Colony

20 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Internal Electrification work

20 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Internal work In kasturba Gandhi girl child school

19 Jun 2023

Status : Comments

By: Yogamber Singh Rawat

Application Forwarded to RTI Team.

19 Jun 2023

Status : Acknowledged

By: Yogamber Singh Rawat

Application Acknoledged.

07 Jun 2023

Status : Reverted

By: Gopal Singh Manral

आप द्वारा अनुभव स्तयापन हेतु अपलोड की गयी मेल आई0डी0 सही नहीं है। अतः सही ई-मेल आई0डी0 आपलोड किये जाने हेतु वापस।

07 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Electrical work inside Kasturba Gandhi Girl School.

07 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Electrical Work inside Hospital

07 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work 131/EE/RWD Date. 09/10/2015

07 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Electrical work inside Revenue Colony

07 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work 52/EE/RES DAte 10/10/2012 Electrical work inside Rajshishu Sadan.

06 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Electrical work inside Kasturba Gandhi Girl School.

06 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Electrical Work inside Hospital

06 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work 131/EE/RWD Date. 09/10/2015

06 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Electrical work inside Revenue Colony

06 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work 52/EE/RES DAte 10/10/2012 Electrical work inside Rajshishu Sadan.

05 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Electrical Work inside Hospital

05 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work 131/EE/RWD Date. 09/10/2015

05 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Electrical work inside Revenue Colony

05 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work 52/EE/RES DAte 10/10/2012 Electrical work inside Rajshishu Sadan.

05 Jun 2023

Status : In-Process

By: Gopal Singh Manral

Mail Has been send for Verification of work Electrical work inside Kasturba Gandhi Girl School.

05 Jun 2023

Status : Comments

By: Yogamber Singh Rawat

Application Forwarded to RTI Team.

05 Jun 2023

Status : Acknowledged

By: Yogamber Singh Rawat

Application Acknoledged.


Sl No On Date Officer Status Remarks
1 10 Jul 2023 Girish Chandra Arya Registration Granted Approved as per approval, verification and recommendation of concern officers and employees.
2 10 Jul 2023 Prem Singh Nabiyal In-Process @Girish Chandra Arya(010099552) ji, Application has been forwarded to you, kindly do the needfull. comments : As per the recommendation of EE the approval for registration in Electrical Class A category may be accorded
3 28 Jun 2023 Balram Misra In-Process @Prem Singh Nabiyal(570068221) ji, Application has been forwarded to you, kindly do the needfull. comments : ठेकेदार द्वारा प्रस्तुत अभिलेखों का सत्यापन प्राप्त हो चुका है। अतः ठेकेदार का विद्युत कार्य श्रेणी ए में पंजीकरण के नवीनीकरण पर विचार करना चाहें।
4 22 Jun 2023 Gopal Singh Manral In-Process @Balram Misra(420010048) ji, Application has been forwarded to you, kindly do the needfull. comments : ठेकेदार द्वारा प्रस्तुत अभिलेखों का सत्यापन प्राप्त हो चुका है। अतः ठेकेदार का विद्युत कार्य श्रेणी ए में पंजीकरण के नवीनीकरण पर विचार करना चाहें।
5 22 Jun 2023 Gopal Singh Manral In-Process work Internal Electrification work has been approved by Gopal Singh Manral
6 22 Jun 2023 Gopal Singh Manral In-Process work Internal Electrification work in Revenue Colony has been approved by Gopal Singh Manral
7 22 Jun 2023 Gopal Singh Manral In-Process work Internal Electrification work has been approved by Gopal Singh Manral
8 22 Jun 2023 Gopal Singh Manral In-Process work Internal Electrification work has been approved by Gopal Singh Manral
9 22 Jun 2023 Gopal Singh Manral In-Process work Internal work In kasturba Gandhi girl child school has been approved by Gopal Singh Manral
10 21 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Internal Electrification work
11 21 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Internal Electrification work
12 21 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Internal Electrification work
13 21 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Internal Electrification work
14 21 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Internal Electrification work
15 21 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Internal Electrification work
16 21 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Internal Electrification work
17 21 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Internal work In kasturba Gandhi girl child school
18 21 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Internal Electrification work
19 21 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Internal Electrification work
20 21 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Internal Electrification work in Revenue Colony
21 21 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Internal Electrification work
22 20 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Internal Electrification work
23 20 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Internal Electrification work
24 20 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Internal Electrification work in Revenue Colony
25 20 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Internal Electrification work
26 20 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Internal work In kasturba Gandhi girl child school
27 19 Jun 2023 Yogamber Singh Rawat Comments Application Forwarded to RTI Team.
28 19 Jun 2023 Yogamber Singh Rawat Acknowledged Application Acknoledged.
29 07 Jun 2023 Gopal Singh Manral Reverted आप द्वारा अनुभव स्तयापन हेतु अपलोड की गयी मेल आई0डी0 सही नहीं है। अतः सही ई-मेल आई0डी0 आपलोड किये जाने हेतु वापस।
30 07 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Electrical work inside Kasturba Gandhi Girl School.
31 07 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Electrical Work inside Hospital
32 07 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work 131/EE/RWD Date. 09/10/2015
33 07 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Electrical work inside Revenue Colony
34 07 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work 52/EE/RES DAte 10/10/2012 Electrical work inside Rajshishu Sadan.
35 06 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Electrical work inside Kasturba Gandhi Girl School.
36 06 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Electrical Work inside Hospital
37 06 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work 131/EE/RWD Date. 09/10/2015
38 06 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Electrical work inside Revenue Colony
39 06 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work 52/EE/RES DAte 10/10/2012 Electrical work inside Rajshishu Sadan.
40 05 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Electrical Work inside Hospital
41 05 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work 131/EE/RWD Date. 09/10/2015
42 05 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Electrical work inside Revenue Colony
43 05 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work 52/EE/RES DAte 10/10/2012 Electrical work inside Rajshishu Sadan.
44 05 Jun 2023 Gopal Singh Manral In-Process Mail Has been send for Verification of work Electrical work inside Kasturba Gandhi Girl School.
45 05 Jun 2023 Yogamber Singh Rawat Comments Application Forwarded to RTI Team.
46 05 Jun 2023 Yogamber Singh Rawat Acknowledged Application Acknoledged.