1 |
16 May 2023
|
Girish Chandra Arya
|
Registration Granted
|
Approved as per verification, approval and recommendation by officers and concern employees.
|
2 |
28 Apr 2023
|
Prem Singh Nabiyal
|
In-Process
|
@Girish Chandra Arya(010099552) ji, Application has been forwarded to you, kindly do the needfull. comments : forwarded for registration as per the recomendation of EE
|
3 |
13 Apr 2023
|
Balram Misra
|
In-Process
|
@Prem Singh Nabiyal(570068221) ji, Application has been forwarded to you, kindly do the needfull. comments : सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत। Pay slip of technical staff has been uploaded in Memorandum of Association.
|
4 |
06 Apr 2023
|
Kedar Singh
|
In-Process
|
@Balram Misra(420010048) ji, Application has been forwarded to you, kindly do the needfull. comments : EE Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत। Pay slip of technical staff has been uploaded in Memorandum of Association.
|
5 |
06 Apr 2023
|
Kedar Singh
|
In-Process
|
@Balram Misra(420010048) ji, Application has been forwarded to you, kindly do the needfull. comments : EE Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में building कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत। Pay slip of technical staff has been uploaded in Memorandum of Association.
|
6 |
06 Apr 2023
|
Yogamber Singh Rawat
|
In-Process
|
Application Forwarded to Parkeen Team.
|
7 |
06 Apr 2023
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
8 |
29 Mar 2023
|
Kedar Singh
|
Reverted
|
submit pay slip of technical staff
|
9 |
24 Mar 2023
|
Balram Misra
|
In-Process
|
@Kedar Singh(010090330) ji, Application has been forwarded to you, kindly do the needfull. comments : As per clause 10 Appendix C of SOP of contractors registration please ensure to submit pay slip of technical staff and than put up
|
10 |
23 Mar 2023
|
Prem Singh Nabiyal
|
In-Process
|
@Balram Misra(420010048) ji, Application has been forwarded to you, kindly do the needfull. comments : As per clause 10 Appendix C of SOP of contractors registration please ensure to submit pay slip of technical staff and than put up
|
11 |
23 Mar 2023
|
Balram Misra
|
In-Process
|
@Prem Singh Nabiyal(570068221) ji, Application has been forwarded to you, kindly do the needfull. comments : Sir, Pay Slip of tech Staff not submitted but mentioned in Lump sum, so it may be looked into.
|
12 |
23 Mar 2023
|
Balram Misra
|
In-Process
|
@Prem Singh Nabiyal(570068221) ji, Application has been forwarded to you, kindly do the needfull. comments : Application has been forwarded to you, kindly do the needfull. comments : Section में सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत।
|
13 |
23 Mar 2023
|
Kedar Singh
|
In-Process
|
@Balram Misra(420010048) ji, Application has been forwarded to you, kindly do the needfull. comments : EE Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत।
|
14 |
08 Feb 2023
|
Kedar Singh
|
In-Process
|
@Anil Kumar Pangty(010096073) ji, Application has been forwarded to you, kindly do the needfull. comments : S.S.O. Sir सत्यापन की कार्यवाही पूर्ण हो चूकी है। अतः विभाग में ठेकेदारों की सूची श्रेण ‘‘ए’’ में Road कार्य हेतु पंजीकरण करना चाहें। कृपया आदेशार्थ प्रस्तुत।
|
15 |
08 Feb 2023
|
Kedar Singh
|
In-Process
|
work Purola to Chhara gaon m/r stage_II has been approved by Kedar Singh
|
16 |
08 Feb 2023
|
Kedar Singh
|
In-Process
|
work Purola to Chhara gaon m/r (Stage_I) has been approved by Kedar Singh
|
17 |
08 Feb 2023
|
Kedar Singh
|
In-Process
|
work Syalna dang to Sartall MR Stage_II has been approved by Kedar Singh
|
18 |
08 Feb 2023
|
Kedar Singh
|
In-Process
|
work Nakuri to singot Motor road stage_II has been approved by Kedar Singh
|
19 |
08 Feb 2023
|
Kedar Singh
|
In-Process
|
work Protection work in km. 1.00 on Durgadwar Ganai to Nityawada motor road. has been approved by Kedar Singh
|
20 |
02 Feb 2023
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Syalna dang to Sartall MR Stage_II
|
21 |
02 Feb 2023
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Nakuri to singot Motor road stage_II
|
22 |
28 Jan 2023
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Syalna dang to Sartall MR Stage_II
|
23 |
28 Jan 2023
|
Kedar Singh
|
In-Process
|
work Syalna dang to Sartall MR Stage_II has been dis-approved by Kedar Singh
|
24 |
28 Jan 2023
|
Kedar Singh
|
In-Process
|
Mail Has been send for Verification of work Nakuri to singot Motor road stage_II
|
25 |
19 Jan 2023
|
Mahendra Kumar
|
In-Process
|
Mail Has been send for Verification of work Purola to Chhara gaon m/r stage_II
|
26 |
19 Jan 2023
|
Mahendra Kumar
|
In-Process
|
Mail Has been send for Verification of work Purola to Chhara gaon m/r (Stage_I)
|
27 |
19 Jan 2023
|
Mahendra Kumar
|
In-Process
|
Mail Has been send for Verification of work Nakuri to singot Motor road stage_II
|
28 |
13 Jan 2023
|
Mahendra Kumar
|
In-Process
|
Mail Has been send for Verification of work Purola to Chhara gaon m/r (Stage_I)
|
29 |
13 Jan 2023
|
Mahendra Kumar
|
In-Process
|
Mail Has been send for Verification of work Syalna dang to Sartall MR Stage_II
|
30 |
13 Jan 2023
|
Mahendra Kumar
|
In-Process
|
Mail Has been send for Verification of work Nakuri to singot Motor road stage_II
|
31 |
13 Jan 2023
|
Mahendra Kumar
|
In-Process
|
Mail Has been send for Verification of work Purola to Chhara gaon m/r stage_II
|
32 |
13 Jan 2023
|
Mahendra Kumar
|
In-Process
|
Mail Has been send for Verification of work Protection work in km. 1.00 on Durgadwar Ganai to Nityawada motor road.
|
33 |
13 Jan 2023
|
Anil Kumar Pangty
|
Comments
|
@Mahendra Kumar(420010235) ji, Application has been forwarded to you, kindly do the needfull. comments : समस्त प्रमाण पत्रों को सत्यापन कर प्रस्तुत करें।
|
34 |
13 Jan 2023
|
Mahendra Kumar
|
Comments
|
@Anil Kumar Pangty(010096073) ji, Application has been forwarded to you, kindly do the needfull. comments : S.S.O. Sir अनुभव प्रमाण पत्र/हेसियत/चरित्र प्रमाण पत्र के सत्यापन की कार्यवाही हेतु आदेशित करना चाहे।
|
35 |
11 Jan 2023
|
Mahendra Kumar
|
Comments
|
@Anil Kumar Pangty(010096073) ji, Application has been forwarded to you, kindly do the needfull. comments : S.S.O. Sir अनुभव प्रमाण पत्र/हेसियत/चरित्र प्रमाण पत्र के सत्यापन की कार्यवाही हेतु आदेशित करना चाहे।
|
36 |
11 Jan 2023
|
Yogamber Singh Rawat
|
Comments
|
Application Forwarded to Parkeen Team.
|
37 |
11 Jan 2023
|
Yogamber Singh Rawat
|
Comments
|
Application Forwarded to Parkeen Team.
|
38 |
11 Jan 2023
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
39 |
30 Sep 2022
|
Kedar Singh
|
Reverted
|
1 more road exp. is required.
|
40 |
23 Sep 2022
|
Anil Kumar Pangty
|
Comments
|
@Mahendra Kumar(420010235) ji, Application has been forwarded to you, kindly do the needfull. comments : अनुभव प्रमाण पत्र मार्ग कार्य हेतु लिया जा सकता है।
|
41 |
22 Sep 2022
|
Mahendra Kumar
|
Comments
|
@Anil Kumar Pangty(010096073) ji, Application has been forwarded to you, kindly do the needfull. comments : S.S.O Sir फर्म द्वारा प्रस्तुत पांच अनुभव प्रमाण पत्र में प्रस्तुत किया जिसमें प्रा0ख0 लो0नि0वि0 रूद्रप्रयाग द्वारा जारी अनुभव प्रमाण पत्र का अनुबन्ध संख्या 21 ई0ई0 दिनांक 24.02.2018 रु0 20.61 लाख में walling लिखा है अतः अग्रिम कार्यवाही हेतु आदेशित करना चाहे।
|
42 |
20 Sep 2022
|
Yogamber Singh Rawat
|
Comments
|
Application Forwarded to Parkeen Team.
|
43 |
20 Sep 2022
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
44 |
15 Sep 2022
|
Mahendra Kumar
|
Reverted
|
Rohit singh is also working with dhum singh farswan.
|
45 |
09 Sep 2022
|
Mahendra Kumar
|
Reverted
|
Rohit singh is also working with dhum singh farswan.
|
46 |
27 Aug 2022
|
Yogamber Singh Rawat
|
Comments
|
Application Forwarded to Parkeen Team.
|
47 |
27 Aug 2022
|
Yogamber Singh Rawat
|
Acknowledged
|
Application Acknoledged.
|
48 |
04 Jul 2022
|
Mahendra Kumar
|
Reverted
|
Pan card Of Miss. Ishita should be uploaded.
Latest GST should be uploaded.
Degree of Shri avinash is provisional.
Identitiy of Shri raj vardhan should be uploaded.
Power of attorney should be uploaded.
|
49 |
30 Jun 2022
|
Yogamber Singh Rawat
|
Comments
|
Application Forwarded to Parkeen Team.
|
50 |
30 Jun 2022
|
Yogamber Singh Rawat
|
Acknowledged
|